GOLD 4160.30 −0.5% SILVER 57.27 −0.1% COPPER 6.58 +0.2% OIL 98.54 −0.5% PALLADIUM 1119.00 +0.0% BGAU 1.01 −1.9% ESK 0.205 −2.4% BEX 0.080 +6.7% PMX 0.080 +0.0% ZNX 0.280 −3.5% HHH 4.01 −3.1% SRL 0.335 −1.5% WGX 4.82 −1.8% WCU 0.130 +8.3% SAGE 0.110 +0.0% BHS 0.060 +20.0% BARU 0.055 +22.2% REC 0.050 +0.0% NICN 0.115 +0.0% TRX 1.48 −2.0% VLC 0.220 +4.8% GOLD 4160.30 −0.5% SILVER 57.27 −0.1% COPPER 6.58 +0.2% OIL 98.54 −0.5% PALLADIUM 1119.00 +0.0% BGAU 1.01 −1.9% ESK 0.205 −2.4% BEX 0.080 +6.7% PMX 0.080 +0.0% ZNX 0.280 −3.5% HHH 4.01 −3.1% SRL 0.335 −1.5% WGX 4.82 −1.8% WCU 0.130 +8.3% SAGE 0.110 +0.0% BHS 0.060 +20.0% BARU 0.055 +22.2% REC 0.050 +0.0% NICN 0.115 +0.0% TRX 1.48 −2.0% VLC 0.220 +4.8%
Drill Results

Pulsar Helium Reports Commencement of Jetstream #7 and Completion of Seismic Survey at the Topaz Helium Project, USA

PLSR · Price

Executive Summary

  • Completed drilling of Jetstream #6 to a total depth of 2,597 ft, intersecting multiple pressurised gas zones that confirm the Topaz geological model.
  • Mobilised the rig to commence drilling of Jetstream #7 (TD ≈ 3,000 ft, potential to deepen to 5,000 ft) as a significant step‑out appraisal well.
  • Finished an extensive 2D active seismic program across the Topaz Project – five lines totaling 41.5 mi – with data validated as good quality and now being processed for interpretation.

Key Details

  • Jetstream #6 Completion
  • Total depth (TD): 2,597 ft.
  • Pressurised gas intervals encountered:
    • 1,287 ft (~576 psi)
    • 2,120 ft (~981 psi)
    • 2,187 ft (~1,012 psi)
    • 2,377 ft (~1,100 psi)
  • Gas observed bubbling to surface during drilling; continuous HQ core retrieved.

  • Jetstream #7 Status

  • Drilling commenced 19 Feb 2026; surface casing set and cemented.
  • Current depth: 737 ft (as of announcement).
  • Planned TD: 3,000 ft with option to deepen to 5,000 ft.
  • Location: ~2.2 mi NW of Jetstream #1 – a step‑out appraisal well aimed at expanding the Topaz resource footprint.

  • 2D Seismic Program

  • Five seismic lines acquired, total length 41.5 mi, completed 20 Feb 2026.
  • Low‑impact Vibroseis sources and wireless geophone nodes used for high‑resolution imaging.
  • Raw data QA/QC‑reviewed onsite by an independent contractor; deemed good quality.
  • Data transferred to Earth Signal (Calgary) for processing; interpretation will be performed in‑house to refine structural mapping, support resource assessment, and guide future drilling targets.

  • Operational Context

  • Topaz Project now has six drilled appraisal wells with a 100 % success rate of intersecting pressurised gas; Jetstream #7 is the seventh well.
  • Ongoing technical work focuses on expanding understanding of helium, helium‑3 and CO₂ occurrences within the reservoir.

Notable Quotes

  • “The successful completion of Jetstream #6 and the commencement of Jetstream #7, together with our newly acquired seismic dataset, provide a robust foundation for advancing the Topaz Project toward its next development milestones.” – Thomas Abraham‑James, President, CEO & Director, Pulsar Helium Inc.