S 0.140 +0.0% BNKR 4.40 −2.2% QRO 0.045 +0.0% VCT 0.075 +36.4% PPP 1.15 +0.9% LMG 0.390 +0.0% GRDM 0.140 +0.0% ABRA 13.58 −4.1% WHY 0.295 +1.7% HHH 3.94 −0.2% COS 0.060 +0.0% NOB 0.065 −23.5% MEK 0.055 +0.0% TGOL 0.105 −4.5% FCI 0.400 −7.0% SGQ 0.350 +0.0% S 0.140 +0.0% BNKR 4.40 −2.2% QRO 0.045 +0.0% VCT 0.075 +36.4% PPP 1.15 +0.9% LMG 0.390 +0.0% GRDM 0.140 +0.0% ABRA 13.58 −4.1% WHY 0.295 +1.7% HHH 3.94 −0.2% COS 0.060 +0.0% NOB 0.065 −23.5% MEK 0.055 +0.0% TGOL 0.105 −4.5% FCI 0.400 −7.0% SGQ 0.350 +0.0%
Technical Study Material +

RPX Gold Inc. Delivers Robust Preliminary Economic Assessment and Updated Mineral Resource Estimate for Wawa Gold Project

RPX Gold Delivers High-IRR PEA, But Aggressive US$3,500 Gold "Base Case" Masks Execution Risks

Executive Summary

The most recent news (February 18, 2026) announces a Preliminary Economic Assessment (PEA) and an updated Mineral Resource Estimate (MRE) for the 100%-owned Wawa Gold Project in Ontario. Key highlights include an after-tax NPV5% of C$523M and an exceptional IRR of 99.7%. The study proposes a phased approach: initial small-scale open-pit mining transitioning to underground operations, utilizing third-party toll milling. The project has a 9-year mine life with an initial capital requirement of only C$51.2M and a payback period of 0.9 years. The MRE shows a 48% increase in Indicated gold ounces to 1.24M oz (at 1.79 g/t), with 509k oz in the Inferred category.

Material Impact

The impact is Material - Positive, but carries significant caveats. - Fundamental Impact: The economics are robust on paper, specifically the exceptionally low initial CAPEX (C$51.2M) and the high IRR. This is achieved by assuming a toll milling scenario which avoids the massive upfront cost of building a mill and tailings facility. - Critical Risk (Gold Price): The NPV and IRR are calculated using a US$3,500/oz gold "base case." This is significantly above current spot prices and industry standards for PEAs (typically US$1,850 - US$2,100). Using such an inflated base case artificially boosts the project's perceived value and sustainability. - Operational Risk: The entire economic model relies on a toll milling agreement that has not yet been obtained. Without this, the CAPEX and permitting timelines would increase drastically. - Historical Context: This news represents a full recovery from the 2024 assay manipulation scandal under the former CEO. The new management team has successfully verified the database and delivered a development path, restoring credibility to the asset.

RPX · Price
Company Overview

RPX Gold (formerly Red Pine Exploration) owns 100% of the Wawa Gold Project in Ontario. The project is situated in a prolific mining camp near the Island Gold Mine (Alamos Gold) and the Magino Mine. - Flagship Project: Wawa Gold Project, host to the Surluga and Minto deposits. - Development Stage: PEA complete, moving toward PFS. - Focus: Transitioning from exploration to a low-capital producer via phased open-pit development.