GOLD 4407.30 −1.2% SILVER 64.93 −5.4% COPPER 6.55 −5.0% OIL 102.48 +6.7% PALLADIUM 1294.70 −6.2% IGO 0.190 −2.6% MCI 0.165 −2.9% GGI 0.080 +6.7% ETF 0.040 −11.1% ADE 0.100 +5.3% WDO 33.52 −3.3% IMM 0.065 +8.3% SNAG 0.240 −7.7% TUF 0.670 −2.9% VZZ 0.245 −3.9% APGO 3.55 +12.0% ISO 15.38 −6.6% VCG 1.52 +1.3% WRX 0.040 +0.0% TLG 2.22 −4.7% BARU 0.060 +0.0% GOLD 4407.30 −1.2% SILVER 64.93 −5.4% COPPER 6.55 −5.0% OIL 102.48 +6.7% PALLADIUM 1294.70 −6.2% IGO 0.190 −2.6% MCI 0.165 −2.9% GGI 0.080 +6.7% ETF 0.040 −11.1% ADE 0.100 +5.3% WDO 33.52 −3.3% IMM 0.065 +8.3% SNAG 0.240 −7.7% TUF 0.670 −2.9% VZZ 0.245 −3.9% APGO 3.55 +12.0% ISO 15.38 −6.6% VCG 1.52 +1.3% WRX 0.040 +0.0% TLG 2.22 −4.7% BARU 0.060 +0.0%
Financings

Altiplano talks work for Santa Beatriz, El Penon

APN · Price

Executive Summary

  • Altiplano Metals entered a short‑term agreement with Andes Core Mining to rent its Santa Beatriz mine and El Penón processing plant, generating $31,625 in rental income from 3,953 t mined between November and January.
  • The contractor‑driven mining program was suspended; both the mine and plant are now on short‑term care‑and‑maintenance while a strategic review of the rental model is undertaken.
  • Altiplano closed its previously announced private placement of 21,194,300 units at $0.05 per unit, raising $1,059,715 in gross proceeds; each unit includes one common share and half a non‑transferable warrant exercisable at $0.075 until 19 Dec 2027.

Key Details

  • Short‑Term Mining & Processing Agreement
  • Contractor: Andes Core Mining (ACM).
  • Rental fee to Altiplano: US$8 per tonne of material mined at Santa Beatriz.
  • Plant rental income: US$30,000 per month.
  • ACM responsible for all operating costs, royalties, personnel, development, sustainability and maintenance.
  • Production & Income (Nov–Jan)
  • Total material mined: 3,953 t.
  • Rental income earned: US$31,625.
  • Development Focus
  • Levels targeted: 425 m, 400 m, 392 m; ceiling work at 400 m and 391 m.
  • Advancement to 382 m level achieved 30 m of the planned 80 m.
  • Strategic Pause
  • Both Santa Beatriz mine and El Penón plant placed on short‑term care and maintenance.
  • Company reviewing outcomes and alternative strategies to enhance shareholder returns, including possible continuation of the rental concept.
  • Private Placement Closure
  • Units sold: 21,194,300 at US$0.05 per unit.
  • Gross proceeds: US$1,059,715.
  • Unit composition: 1 common share + ½ non‑transferable warrant (exercisable at US$0.075 per share).
  • Warrant expiry: 19 Dec 2027.

Notable Quotes

  • Alastair McIntyre, President & CEO: “The decision to use a contractor to develop the mine infrastructure to deeper levels focused on a cost‑effective approach… Operations have been paused while this strategic review is under way.”
Read the original news release →