G Mining Ventures Reports Q1 2026 Preliminary Gold Production of 31,846 oz
G Mining Ventures Production Confirms Guidance Amidst Major Guyana Acquisition Integration

Executive Summary
- G Mining Ventures Corp. reported preliminary Q1 2026 gold production of 31,846 oz from its Tocantinzinho (TZ) mine in Brazil.
- Results were in line with company expectations and guidance for the quarter.
- Production was characterized by planned mining of lower-grade material to facilitate waste stripping and pit advancement for Phase 2 mineralization access.
- The company maintains full-year 2026 production guidance of 160,000 to 190,000 ounces of gold.
- Approximately 62% of annual output is expected in the second half of 2026 as higher-grade Phase 2 mineralization is accessed.
- Average plant throughput was 11,811 tpd with a recovery rate of 90.3%.
Material Impact
- The Q1 production update validates the operational stability of the Tocantinzinho mine, which serves as the primary cash flow engine for funding the Oko West project and the recent G2 Goldfields acquisition.
- While positive, the news is classified as Routine - Positive because it confirms existing guidance rather than introducing unexpected upside or downside surprises.
- The strategic context remains dominated by the April 9th acquisition of G2 Goldfields (rated Material - Game Changer), which creates a Tier-One gold hub in Guyana; this production report supports the financial capacity to execute that deal.
- No material changes to valuation drivers were introduced, as the guidance for FY 2026 remains unchanged from previous announcements.
GMIN · Price
Company Overview
- Company: G Mining Ventures Corp. is an intermediate gold producer with operations in Brazil (Tocantinzinho) and Guyana (Oko West).
- Flagship Project (Operating): Tocantinzinho Gold Mine (TZ), 100%-owned, located in Brazil. FY 2025 production was 171,871 oz with AISC of $1,155/oz.
- Flagship Project (Development): Oko West Gold Project, 100%-owned, Guyana. Feasibility Study indicates 4.64 Moz P&P reserves at 1.89 g/t Au. First gold targeted H2 2027.
- Acquisition: G2 Goldfields Inc. (Oko-Ghanie Project) acquired via Plan of Arrangement, creating a combined "Oko" hub with >500 koz LOM average production potential.
- Exploration: Gurupi Project in Brazil, 1.83 Moz Indicated resources, targeting updated MRE and PEA by end of 2026.