Artemis Gold Reports Unplanned Mill Shutdown at Blackwater

ARTG · Price
Executive Summary
- Artemis Gold announced an unplanned shutdown of the ball mill at its Blackwater Mine due to a gearbox failure on March 11, 2026.
- Repairs are expected to take 8‑10 days; mining activities continue while milling is halted.
- Q1 2026 production will be lower than previously anticipated, though full‑year gold production guidance (265,000–290,000 oz) remains unchanged pending mitigation plans.
Key Details
- Failure: Ball mill gearbox malfunction on 11 Mar 2026.
- Replacement: Suitable spare gearbox is on hand; repair work scheduled for 8–10 days.
- Maintenance: Planned Q2‑2026 maintenance activities will be performed during the outage.
- Operations: Mining continues normally; only milling is affected.
- Production Impact: Q1 2026 output expected to fall short of original estimates; no revision to full‑year guidance at this time.
- Guidance: Full‑year gold production still projected at 265,000–290,000 oz pending make‑up plans for the Q1 shortfall.