GOLD 4408.90 +0.0% SILVER 65.19 +0.4% COPPER 6.55 +0.0% OIL 100.05 −2.4% PALLADIUM 1323.90 +2.3% PGZ 0.170 +3.0% TMQ 4.55 −1.3% SLI 3.08 −1.0% ROX 0.050 −9.1% USHA 0.045 +0.0% ALGR 0.710 +2.9% MINE 0.120 −4.0% KC 0.330 +4.8% EMO 0.335 +0.0% CCM 0.700 +4.5% MAI 5.97 −0.7% PPM 0.015 +0.0% CRE 0.370 +10.4% MNO 1.87 +0.5% FEO 0.810 +3.9% LBNK 0.680 −4.2% GOLD 4408.90 +0.0% SILVER 65.19 +0.4% COPPER 6.55 +0.0% OIL 100.05 −2.4% PALLADIUM 1323.90 +2.3% PGZ 0.170 +3.0% TMQ 4.55 −1.3% SLI 3.08 −1.0% ROX 0.050 −9.1% USHA 0.045 +0.0% ALGR 0.710 +2.9% MINE 0.120 −4.0% KC 0.330 +4.8% EMO 0.335 +0.0% CCM 0.700 +4.5% MAI 5.97 −0.7% PPM 0.015 +0.0% CRE 0.370 +10.4% MNO 1.87 +0.5% FEO 0.810 +3.9% LBNK 0.680 −4.2%
Production / Operations

PPX Obtains Authorization for Water Utilization Work at Igor Processing Plant

PPX · Price

Executive Summary

  • PPX Mining Corp. received a Directorial Resolution from Peru’s Water Administrative Authority authorizing water‑utilization works for the Igor CIL and Flotation Plant.
  • The authorization enables installation of a 1,770 m metallic pipeline and two pumping stations to supply water at elevations of 3,070–3,570 m, supporting the plant’s 350 t/d processing capacity.
  • Construction is slated to begin in November 2025 with an expected completion within 98 calendar days, advancing PPX toward final Water Use License approval and plant commissioning.

Key Details

  • Permit: Directorial Resolution No. 0912‑2025‑ANA‑AAA.HCH dated 5 Nov 2025 from the Autoridad Administrativa del Agua (Huarmey Chicama).
  • Scope of Works Authorized:
  • Installation of a 1,770‑meter metallic water pipeline.
  • Construction of two pumping stations to move water from 3,070 m to 3,570 m above sea level (≈500 m vertical lift).
  • Plant Capacity: Designed for 350 tons per day of ore processing, producing doré and precious‑metal concentrates.
  • Construction Schedule: Start – November 2025; Completion – within 98 calendar days of start.
  • Strategic Impact: Milestone toward commissioning the Igor CIL & Flotation Plant and obtaining the final Water Use License required for full operation.
  • CEO Comment (John Thomas): Emphasized the permit’s critical role, water‑recirculation design to minimize consumption, environmental impact, and community relations, underscoring its importance for plant commissioning.

Notable Quotes

“This is a critical permit toward achieving the commissioning of our processing plant. Water is essential to the metallurgical process, and our engineering design incorporates a recirculation system that minimizes consumption, reduces environmental impact, and promotes social responsibility.” – John Thomas, CEO