Northwire Canada EditionSunday, July 26, 2026
Northwire
B 0.150 +0.0% IFOS 2.28 −2.6% IMM 0.060 +0.0% ROCK 3.38 −1.7% NVX 0.250 −7.4% HAR 0.050 +0.0% YGT 0.175 +0.0% GEN 0.070 −nan% CRB 0.040 +14.3% MSA 7.07 +2.2% AEM 204.81 +0.7% OPW 0.105 +5.0% GRL 0.275 −1.8% AIS 0.150 +0.0% CUU 0.580 −1.7% SOMA 0.720 +5.9% B 0.150 +0.0% IFOS 2.28 −2.6% IMM 0.060 +0.0% ROCK 3.38 −1.7% NVX 0.250 −7.4% HAR 0.050 +0.0% YGT 0.175 +0.0% GEN 0.070 −nan% CRB 0.040 +14.3% MSA 7.07 +2.2% AEM 204.81 +0.7% OPW 0.105 +5.0% GRL 0.275 −1.8% AIS 0.150 +0.0% CUU 0.580 −1.7% SOMA 0.720 +5.9%
Production / Operations

PPX Obtains Authorization for Water Utilization Work at Igor Processing Plant

PPX · Price

Executive Summary

  • PPX Mining Corp. received a Directorial Resolution from Peru’s Water Administrative Authority authorizing water‑utilization works for the Igor CIL and Flotation Plant.
  • The authorization enables installation of a 1,770 m metallic pipeline and two pumping stations to supply water at elevations of 3,070–3,570 m, supporting the plant’s 350 t/d processing capacity.
  • Construction is slated to begin in November 2025 with an expected completion within 98 calendar days, advancing PPX toward final Water Use License approval and plant commissioning.

Key Details

  • Permit: Directorial Resolution No. 0912‑2025‑ANA‑AAA.HCH dated 5 Nov 2025 from the Autoridad Administrativa del Agua (Huarmey Chicama).
  • Scope of Works Authorized:
  • Installation of a 1,770‑meter metallic water pipeline.
  • Construction of two pumping stations to move water from 3,070 m to 3,570 m above sea level (≈500 m vertical lift).
  • Plant Capacity: Designed for 350 tons per day of ore processing, producing doré and precious‑metal concentrates.
  • Construction Schedule: Start – November 2025; Completion – within 98 calendar days of start.
  • Strategic Impact: Milestone toward commissioning the Igor CIL & Flotation Plant and obtaining the final Water Use License required for full operation.
  • CEO Comment (John Thomas): Emphasized the permit’s critical role, water‑recirculation design to minimize consumption, environmental impact, and community relations, underscoring its importance for plant commissioning.

Notable Quotes

“This is a critical permit toward achieving the commissioning of our processing plant. Water is essential to the metallurgical process, and our engineering design incorporates a recirculation system that minimizes consumption, reduces environmental impact, and promotes social responsibility.” – John Thomas, CEO

Read the original news release →

More from PPX Mining Corp.