Aftermath Silver Berenguela & Challacollo Project Updates
Aftermath advances its PFS and drilling program while awaiting new assay results to impact the project's economic outlook.

Aftermath Silver Ltd. (AAG) released an operational and exploration progress update rather than a new drill-result announcement. The company confirmed that the Berenguela Preliminary Feasibility Study (PFS) remains on schedule and on budget for publication in early 2027 or Q1 2027. Completed work to date includes gap analysis, infill drilling, metallurgical testwork, geotechnical and hydrogeological drilling, and trade-off studies.
As of July 2026, 4,002 m of the third diamond drilling campaign has been completed at Berenguela. Drilling is now testing the Copper East target, with section lines planned 50 m and 100 m east of AFD139. The release repeats historic intercepts: AFD100 returned 156 m grading 1.12% Cu, 290 g/t Ag and 7.3% Mn; AFD139 returned 69 m at 1.19% Cu and 78 g/t Ag; and a bonanza silver interval of 1.95 m at 14,252 g/t Ag. No new assay results are reported from the current Berenguela program.
At Challacollo, five holes have been completed totalling 630 m, four on Lolon and one on Lucy, and the program is being extended to 2,000 m. No new Challacollo assays are provided; the release includes only the prior 2020 NI 43-101 Challacollo resource table.
Aftermath Silver Ltd. (AAG) issued an operational update that does not alter the Berenguela or Challacollo mineral resource estimates, project economics, or recoveries. The Pre-Feasibility Study (PFS) remains on schedule for early 2027.
The stock reached a 52-week high of C$1.31 in January 2026 before declining to C$0.62 by late June 2026. It has since recovered modestly to C$0.81. The market has not aggressively bid the stock higher leading into this update. The announcement confirms that the drilling program is active, a fact already known from the July 22, 2026, drilling-start announcement.
Aftermath Silver Ltd. (AAG) is a Canada-listed junior explorer and developer with no revenue and no operating mine. The company’s primary assets include the 100% owned Berenguela silver-copper-manganese project in Peru, the 100% owned Challacollo low-sulphidation epithermal silver-gold project in Chile, and an additional silver-gold project in Cachinal, Chile.
Prior resource data provides context for the company’s holdings. The Berenguela Measured and Indicated resource contained approximately 122.5 moz Ag, 717.1 Mlb Cu, and 2.93 Mt Mn. The project could also carry significant manganese value, with HPMSM described as the primary economic driver. The Challacollo resource, as per the 2020 MRE repeated in the release, contains 35,150 koz Ag and 58 koz Au indicated, plus 11,144 koz Ag and 15 koz Au inferred.
Financial data to February 28, 2026, showed no revenue, a nine-month net loss of C$10.65 million, cash of C$12.12 million, and working capital of C$24.76 million. No long-term debt was reported, but the MD&A includes a going-concern flag. Shares outstanding in the most recently provided financials were 338,864,488.