EAU 0.085 +0.0% MCM 0.310 +0.0% BAT 0.100 +5.3% SFR 0.370 +68.2% FFU 0.125 +4.2% TVI 0.045 −10.0% ZNX 0.080 +0.0% TSK 1.06 +0.9% OMM 0.050 +0.0% EMO 0.320 −7.2% GGA 5.95 +12.3% MDM 0.060 +0.0% WGX 4.29 −3.2% FL 0.410 +0.0% SSRM 35.84 −1.4% CD 0.240 +4.3% EAU 0.085 +0.0% MCM 0.310 +0.0% BAT 0.100 +5.3% SFR 0.370 +68.2% FFU 0.125 +4.2% TVI 0.045 −10.0% ZNX 0.080 +0.0% TSK 1.06 +0.9% OMM 0.050 +0.0% EMO 0.320 −7.2% GGA 5.95 +12.3% MDM 0.060 +0.0% WGX 4.29 −3.2% FL 0.410 +0.0% SSRM 35.84 −1.4% CD 0.240 +4.3%
Production / Operations

PowerBank Expects 4.99 MW BESS Project to Reach Commercial Operating during January 2026

SUNN · Price

Executive Summary

  • PowerBank expects its SFF‑06 Battery Energy Storage System (4.99 MW) in Ontario to achieve Commercial Operation during January 2026.
  • The project secures a 22‑year IESO contract paying $1,221 per MW per business day, well above market averages.
  • PowerBank incurred a $475,000 termination fee and $100,000 retrofit cost for the OZ‑1 project, plus a $512,000 warranty expense for SFF‑06 and the 903 project.

Key Details

  • Project Scope: SFF‑06 BESS will deliver 4.74 MW of daily contract capacity for 251 business days per year once in commercial operation.
  • Ownership: PowerBank holds a 50 % stake in ProjectCo (1000234763 Ontario Inc.); the remaining 50 % is owned by an Ontario First Nations partnership.
  • Acquisition Background: Acquired via PowerBank’s $45 M purchase of Solar Flow‑Through Funds Ltd. (July 2024).
  • Contract Terms: Fixed capacity payment of $1,221 per MW per business day under IESO Expedited Long‑Term RFP (E‑LT1), 22‑year term.
  • Incentives: Qualifies for the 2024 Clean Technology Investment Tax Credit (up to 30 % reimbursement of eligible capital costs).
  • Termination & Costs:
  • OZ‑1 equipment supply and service agreements terminated; PowerBank pays $475,000 termination fee + $100,000 retrofit cost reimbursement.
  • Extended warranty purchased for SFF‑06 and 903 projects at a cost of $512,000.
  • Risk Factors Highlighted: Need for final technical/regulatory approvals, battery degradation over cycles, potential changes to government incentives, and other forward‑looking uncertainties.