S 0.140 +0.0% BNKR 4.40 −2.2% QRO 0.045 +0.0% VCT 0.075 +36.4% PPP 1.15 +0.9% LMG 0.390 +0.0% GRDM 0.140 +0.0% ABRA 13.58 −4.1% WHY 0.295 +1.7% HHH 3.94 −0.2% COS 0.060 +0.0% NOB 0.065 −23.5% MEK 0.055 +0.0% TGOL 0.105 −4.5% FCI 0.400 −7.0% SGQ 0.350 +0.0% S 0.140 +0.0% BNKR 4.40 −2.2% QRO 0.045 +0.0% VCT 0.075 +36.4% PPP 1.15 +0.9% LMG 0.390 +0.0% GRDM 0.140 +0.0% ABRA 13.58 −4.1% WHY 0.295 +1.7% HHH 3.94 −0.2% COS 0.060 +0.0% NOB 0.065 −23.5% MEK 0.055 +0.0% TGOL 0.105 −4.5% FCI 0.400 −7.0% SGQ 0.350 +0.0%
Production / Operations

Grande Portage obtains permit at New Amalga

GPG · Price

Executive Summary

  • Grande Portage secured a five‑year fish habitat permit and is pursuing a special use permit for stream monitoring, advancing environmental baseline data collection.
  • Completed geotechnical/hydrogeological review, aerial LiDAR survey, and commissioned ore offtake studies to support the upcoming Preliminary Economic Assessment (PEA).
  • Retained NEPA consultant Ensight LLC and highlighted a new Alaska‑FAST‑41 permitting pathway that could streamline future approvals.

Key Details

  • Fish Habitat Permit: Five‑year permit from Alaska Department of Fish & Game for installing a stream‑level monitoring system on the Herbert River; installation pending special use permit from U.S. Forest Service.
  • Geotechnical Review: SRK Consulting finished an initial geotechnical and hydrogeological assessment to inform PEA and guide further fieldwork on groundwater and rock behavior.
  • LiDAR Survey: Completed aerial LiDAR scan of potential infrastructure zones and access road corridor; combined with existing terrain data for engineering design of surface facilities.
  • Ore Offtake Studies: Two independent studies contracted to evaluate direct‑to‑smelter options, gold payability, and transportation costs for sorted ore from New Amalga.
  • NEPA Consulting: Engaged Ensight LLC (Charles Johnson) to prepare NEPA documentation; consultant brings 30+ years of experience, including work on the Greens Creek mine EIS (2024).
  • FAST‑41 Program: Memorandum of Understanding signed on Aug 27 between State of Alaska and Federal Permitting Improvement Steering Council to enable streamlined permitting via FAST‑41. Grande Portage views this as a potential fast‑track for project approval.
  • Project Configuration: Plans envision a small‑footprint underground mine with off‑site processing by a third party, avoiding on‑site ore processing plant or tailings landfill; proximity to tidewater and highway supports this approach.
  • Qualified Person: Kyle Mehalek, PE, reviewed and approved the technical disclosure under NI 43‑101; independent of Grande Portage.