GOLD 4321.20 +0.5% SILVER 64.80 +1.2% COPPER 6.77 −0.3% OIL 92.41 −2.3% PALLADIUM 1276.00 −0.5% SMP 0.055 +0.0% NVX 1.10 +12.2% AORO 0.015 +0.0% HAWK 0.025 +25.0% LOD 0.400 +0.0% SBMI 0.135 +3.9% PA 0.160 +3.2% BARU 0.060 +9.1% MKA 0.800 +8.1% GCN 0.030 +0.0% IAU 2.48 +1.6% CS 14.54 −0.2% LGO 0.750 −22.7% REVX 1.99 +19.2% OMI 0.320 +12.3% VLD 0.430 +0.0% GOLD 4321.20 +0.5% SILVER 64.80 +1.2% COPPER 6.77 −0.3% OIL 92.41 −2.3% PALLADIUM 1276.00 −0.5% SMP 0.055 +0.0% NVX 1.10 +12.2% AORO 0.015 +0.0% HAWK 0.025 +25.0% LOD 0.400 +0.0% SBMI 0.135 +3.9% PA 0.160 +3.2% BARU 0.060 +9.1% MKA 0.800 +8.1% GCN 0.030 +0.0% IAU 2.48 +1.6% CS 14.54 −0.2% LGO 0.750 −22.7% REVX 1.99 +19.2% OMI 0.320 +12.3% VLD 0.430 +0.0%
Production / Operations

Borealis Announces First Gold Pour

BOGO · Price

Executive Summary

  • Borealis Mining completed its first pour of gold‑silver doré from the newly crushed and heap‑leached oxide stockpile, producing 65.6 lb (956.7 troy oz) of doré in two bars.
  • The doré has been shipped to Asahi Refining for assay, refining and eventual sale; preliminary indications suggest an approximate 50/50 gold‑silver split.
  • Heap leaching continues on ~106,000 tons treated with cyanide and an additional 34,000 tons crushed but not yet leached, with a second pour expected within several weeks.

Key Details

  • Production: First genuine doré pour – 65.6 lb (956.7 troy oz) split into one full bar and one partial bar.
  • Assay Outlook: Preliminary results indicate roughly equal gold and silver content plus minor waste metal; final assay pending from Asahi Refining.
  • Processing Volumes:
  • ~106,000 tons of oxide material already treated with cyanide solution on the heap leach pad.
  • Additional ~34,000 tons crushed but not yet subjected to heap leaching.
  • Future Production: Carbon columns are loaded and a second pour is anticipated in “several weeks,” supporting steady near‑term revenue.
  • Strategic Context: The pour marks the first gold‑silver production from fresh oxide material at Borealis, demonstrating successful optimization of crushing, trucking, leach pad operations, and cyanide processing.
  • Forward Plans: Management will update the market on timing for the restart of full‑scale mining operations at the Borealis Mine in the near term.

Notable Quotes

“This is a genuine milestone for our team, the Company, and its shareholders… The result was a perfectly executed pour… Borealis stakeholders can look forward to steady revenue for the next several months…” – Andreas Steckenborn, COO


All boilerplate, forward‑looking disclaimer, and “About the Company” sections have been omitted.

Read the original news release →