Digi Power X's ARMS 200 pod to be delivered in November

DGX · Price
Executive Summary
- Digi Power X’s ARMS 200 modular AI data‑centre platform achieved Tier 3 certification under ANSI/TIA‑942, positioning it among a few worldwide certified solutions.
- The first certified ARMS 200 pod will be delivered to the Alabama facility by end‑Nov 2025 with commissioning in Dec 2025; subsequent ARMS 500 and ARMS 1000 clusters are planned.
- The company reported $29 M of cash, Bitcoin and Ethereum holdings (including 100 BTC and ~1,000 ETH) and disclosed ongoing mining production of ~25 BTC (~$2.8 M) for September 2025.
Key Details
- Tier‑3 Certification: ARMS 200 received Tier 3 status from EPI, confirming 99.982 % availability, redundant systems, and enterprise‑grade reliability for AI, cloud, and blockchain workloads.
- Deployment Timeline: First certified pod to be delivered to Alabama site by 30 Nov 2025; commissioning scheduled for Dec 2025. Full deployment cycle for each ARMS unit is ~180 days from delivery.
- Future Capacity Plans: Expansion roadmap includes ARMS 500 (5 MW) and ARMS 1000 (10 MW) clusters, enabling scalable AI infrastructure with Tier‑3 reliability.
- Strategic Partnership: Deepened alliance with Super Micro Computer Inc., integrating AI‑optimized rack‑scale systems into the ARMS platform to enhance turnkey offering.
- Balance Sheet Highlights (as of 30 Sept 2025):
- Total cash, Bitcoin, Ethereum and deposits ≈ $29 M (unchanged from Aug 2025).
- Bitcoin holdings increased to ~100 BTC (up 18 % month‑over‑month).
- Ethereum holdings ~1,000 ETH valued at ~$4.2 M (down from $4.4 M due to price decline).
- Mining Production:
- BTC mined/produced in Sept 2025 ≈ 25 BTC (~$2.8 M at $113,300/BTC).
- Total BTC value generated from mining and co‑location agreements for the month ≈ $3.4 M.
- Capital Expenditures: YTD capex ≈ $5.8 M on mining infrastructure; September 2025 capex ≈ $0.3 M.
- Power Infrastructure: Current available power ~100 MW across three sites; target expansion to 200 MW via organic growth and acquisitions, with next‑gen hydro‑powered miners slated for Q1 2026.
Notable Quotes
“Tier 3 certification for ARMS 200 represents a turning point for Digi Power X… we are building a differentiated platform for hyperscale‑ready AI growth,” – Michel Amar, CEO, Digi Power X.