Northwire Canada EditionSaturday, July 11, 2026
Northwire
GLDN 0.055 +0.0% BRON 0.040 +0.0% BTO 5.43 −0.7% ESK 0.365 −2.7% AUMN 0.275 +0.0% GGX 0.040 +0.0% S 0.155 +29.2% NNX 0.035 +0.0% ABX 51.90 −0.6% TTS 2.40 −4.0% FCI 0.400 −9.1% GR 0.075 +0.0% AII 23.38 +12.4% TUNG 1.72 +1.8% LGO 1.01 −2.9% EMM 0.080 +0.0% GLDN 0.055 +0.0% BRON 0.040 +0.0% BTO 5.43 −0.7% ESK 0.365 −2.7% AUMN 0.275 +0.0% GGX 0.040 +0.0% S 0.155 +29.2% NNX 0.035 +0.0% ABX 51.90 −0.6% TTS 2.40 −4.0% FCI 0.400 −9.1% GR 0.075 +0.0% AII 23.38 +12.4% TUNG 1.72 +1.8% LGO 1.01 −2.9% EMM 0.080 +0.0%
Production / Operations

CHAR Tech Provides Thorold Commissioning Update, Core Process Equipment Installation Advancing

YES · Price

Executive Summary

  • Kiln chamber at the Thorold Renewable Energy Facility is now fully assembled and burner walls welded, marking a key milestone in Phase 1 construction.
  • Mechanical installations are largely complete; commissioning will focus on tie‑ins, controls, and feedstock handling with biomass introduction targeted by month‑end.
  • Phase 1 aims to produce up to 5,000 t/yr of biocarbon, with commercial production ramp‑up expected in Q2 2026; Phase 2 planning (second kiln, methanation, RNG pipeline) is already underway.

Key Details

  • Kiln Chamber: Fully assembled; burner walls welded in place.
  • Thermal Oxidizer: Mounted on mezzanine structure; supporting mechanical installations completed.
  • Commissioning Focus: Sequential start‑up—first feedstock handling/preparation, then full commercial pyrolysis kiln operation.
  • Biomass Feedstock: Introduction to handling system targeted for end of March 2026.
  • Phase 1 Capacity: Up to 5,000 tonnes per year of biocarbon production.
  • Production Ramp‑Up: Targeted to reach commercial levels during Q2 2026.
  • Phase 2 Plans: Installation of a second high‑temperature pyrolysis kiln, addition of methanation equipment to convert synthetic gas into Renewable Natural Gas (RNG), and construction of an on‑site RNG pipeline injection point.
  • CEO Quote: Andrew White emphasized that the project is moving toward first commercial revenues and highlighted the long‑term growth plan for shareholder value.

Notable Quotes

“Our team is successfully advancing phase 1 of the Thorold Renewable Energy Facility construction as we continue with commissioning… We are focused on building shareholder value and milestones like this are just the beginning steps to a long‑term growth plan.” – Andrew White, CEO

Read the original news release →

More from Char Technologies Ltd.