Northwire Canada EditionThursday, October 15, 2026
Northwire
⌕
GOLD 4107.90 −1.7% SILVER 55.88 −6.1% COPPER 6.62 −1.6% OIL 95.09 +1.0% PALLADIUM 1096.50 −2.7% CIA 2.64 −0.4% BTO 7.09 −4.3% MCI 0.155 +0.0% CAN 0.065 +0.0% BLDS 0.335 +8.1% SAO 0.050 +0.0% SF 0.315 +0.0% BEA 0.055 −15.4% BMM 3.90 +11.1% AUGC 0.295 −13.2% MFG 3.34 −3.8% CDE 21.33 −7.7% CYG 0.160 −5.9% RSMX 0.100 −4.8% TUF 0.830 −5.7% GPG 0.285 −3.4% GOLD 4107.90 −1.7% SILVER 55.88 −6.1% COPPER 6.62 −1.6% OIL 95.09 +1.0% PALLADIUM 1096.50 −2.7% CIA 2.64 −0.4% BTO 7.09 −4.3% MCI 0.155 +0.0% CAN 0.065 +0.0% BLDS 0.335 +8.1% SAO 0.050 +0.0% SF 0.315 +0.0% BEA 0.055 −15.4% BMM 3.90 +11.1% AUGC 0.295 −13.2% MFG 3.34 −3.8% CDE 21.33 −7.7% CYG 0.160 −5.9% RSMX 0.100 −4.8% TUF 0.830 −5.7% GPG 0.285 −3.4%
Production / Operations

CHAR Tech Provides Thorold Commissioning Update, Core Process Equipment Installation Advancing

YES · Price

Executive Summary

  • Kiln chamber at the Thorold Renewable Energy Facility is now fully assembled and burner walls welded, marking a key milestone in Phase 1 construction.
  • Mechanical installations are largely complete; commissioning will focus on tie‑ins, controls, and feedstock handling with biomass introduction targeted by month‑end.
  • Phase 1 aims to produce up to 5,000 t/yr of biocarbon, with commercial production ramp‑up expected in Q2 2026; Phase 2 planning (second kiln, methanation, RNG pipeline) is already underway.

Key Details

  • Kiln Chamber: Fully assembled; burner walls welded in place.
  • Thermal Oxidizer: Mounted on mezzanine structure; supporting mechanical installations completed.
  • Commissioning Focus: Sequential start‑up—first feedstock handling/preparation, then full commercial pyrolysis kiln operation.
  • Biomass Feedstock: Introduction to handling system targeted for end of March 2026.
  • Phase 1 Capacity: Up to 5,000 tonnes per year of biocarbon production.
  • Production Ramp‑Up: Targeted to reach commercial levels during Q2 2026.
  • Phase 2 Plans: Installation of a second high‑temperature pyrolysis kiln, addition of methanation equipment to convert synthetic gas into Renewable Natural Gas (RNG), and construction of an on‑site RNG pipeline injection point.
  • CEO Quote: Andrew White emphasized that the project is moving toward first commercial revenues and highlighted the long‑term growth plan for shareholder value.

Notable Quotes

“Our team is successfully advancing phase 1 of the Thorold Renewable Energy Facility construction as we continue with commissioning… We are focused on building shareholder value and milestones like this are just the beginning steps to a long‑term growth plan.” – Andrew White, CEO

Read the original news release →

More from Char Technologies Ltd.