Northwire Canada EditionSunday, November 29, 2026
Northwire
⌕
Gold 3,668.50 +3.8% Silver 43.70 +9.1% Copper 5.52 +3.4% Oil 83.33 −0.4% Palladium 879.00 +5.5% MUN 0.285 +11.8% RNCH 0.030 +0.0% GSKR 2.30 +8.0% ADY 0.370 +5.7% TSK 0.640 +1.6% BAY 0.055 +22.2% CGNT 0.670 −2.9% INFI 0.190 +0.0% GSS 0.045 +50.0% HAY 0.040 +0.0% WRLG 0.430 +1.2% MPVD 0.015 + GGO 0.980 +5.4% NAU 0.530 +6.0% COCO 0.260 +8.3% TBLL 0.045 +12.5% Gold 3,668.50 +3.8% Silver 43.70 +9.1% Copper 5.52 +3.4% Oil 83.33 −0.4% Palladium 879.00 +5.5% MUN 0.285 +11.8% RNCH 0.030 +0.0% GSKR 2.30 +8.0% ADY 0.370 +5.7% TSK 0.640 +1.6% BAY 0.055 +22.2% CGNT 0.670 −2.9% INFI 0.190 +0.0% GSS 0.045 +50.0% HAY 0.040 +0.0% WRLG 0.430 +1.2% MPVD 0.015 + GGO 0.980 +5.4% NAU 0.530 +6.0% COCO 0.260 +8.3% TBLL 0.045 +12.5%
Production / Operations

CHAR Tech Provides Thorold Commissioning Update, Core Process Equipment Installation Advancing

YES · Price

Executive Summary

  • Kiln chamber at the Thorold Renewable Energy Facility is now fully assembled and burner walls welded, marking a key milestone in Phase 1 construction.
  • Mechanical installations are largely complete; commissioning will focus on tie‑ins, controls, and feedstock handling with biomass introduction targeted by month‑end.
  • Phase 1 aims to produce up to 5,000 t/yr of biocarbon, with commercial production ramp‑up expected in Q2 2026; Phase 2 planning (second kiln, methanation, RNG pipeline) is already underway.

Key Details

  • Kiln Chamber: Fully assembled; burner walls welded in place.
  • Thermal Oxidizer: Mounted on mezzanine structure; supporting mechanical installations completed.
  • Commissioning Focus: Sequential start‑up—first feedstock handling/preparation, then full commercial pyrolysis kiln operation.
  • Biomass Feedstock: Introduction to handling system targeted for end of March 2026.
  • Phase 1 Capacity: Up to 5,000 tonnes per year of biocarbon production.
  • Production Ramp‑Up: Targeted to reach commercial levels during Q2 2026.
  • Phase 2 Plans: Installation of a second high‑temperature pyrolysis kiln, addition of methanation equipment to convert synthetic gas into Renewable Natural Gas (RNG), and construction of an on‑site RNG pipeline injection point.
  • CEO Quote: Andrew White emphasized that the project is moving toward first commercial revenues and highlighted the long‑term growth plan for shareholder value.

Notable Quotes

“Our team is successfully advancing phase 1 of the Thorold Renewable Energy Facility construction as we continue with commissioning… We are focused on building shareholder value and milestones like this are just the beginning steps to a long‑term growth plan.” – Andrew White, CEO

Read the original news release →

More from Char Technologies Ltd.