GLDN 0.055 +0.0% BRON 0.040 +0.0% BTO 5.43 −0.7% ESK 0.365 −2.7% AUMN 0.275 +0.0% GGX 0.040 +0.0% S 0.155 +29.2% NNX 0.035 +0.0% ABX 51.90 −0.6% TTS 2.40 −4.0% FCI 0.400 −9.1% GR 0.075 +0.0% AII 23.38 +12.4% TUNG 1.72 +1.8% LGO 1.01 −2.9% EMM 0.080 +0.0% GLDN 0.055 +0.0% BRON 0.040 +0.0% BTO 5.43 −0.7% ESK 0.365 −2.7% AUMN 0.275 +0.0% GGX 0.040 +0.0% S 0.155 +29.2% NNX 0.035 +0.0% ABX 51.90 −0.6% TTS 2.40 −4.0% FCI 0.400 −9.1% GR 0.075 +0.0% AII 23.38 +12.4% TUNG 1.72 +1.8% LGO 1.01 −2.9% EMM 0.080 +0.0%
Production / Operations

Char Technologies progresses with Thorold commissioning

YES · Price

Executive Summary

  • Char Technologies provides a progress update on the commissioning of its Thorold renewable energy facility, confirming that core high-temperature pyrolysis (HTP) system installation is advancing.
  • The company targets the introduction of biomass to the feedstock handling system by the end of the current month, with Phase 1 ramp-up to commercial production levels targeted for the second quarter of 2026.
  • Phase 1 is designed to produce up to 5,000 tonnes per year of biocarbon, with Phase 2 construction planned to follow, including a second HTP kiln and renewable natural gas (RNG) infrastructure.

Key Details

  • Equipment Installation Status:
    • The kiln chamber is now fully assembled.
    • Burner walls have been welded in place.
    • The thermal oxidizer has been mounted on its mezzanine structure.
    • Several supporting mechanical installations required for integrated system operation have been completed.
  • Commissioning Schedule:
    • Activities are proceeding in sequence, starting with feedstock handling and preparation equipment.
    • Focus is shifting toward tie-ins, controls, and operating readiness.
    • Introduction of biomass to the feedstock handling system is targeted by month-end.
  • Production Targets:
    • Phase 1 capacity: Up to 5,000 tonnes per year of biocarbon.
    • Commercial production ramp-up: Targeted for the second quarter of 2026.
  • Future Expansion (Phase 2):
    • Installation of a second HTP kiln.
    • Addition of methanation equipment to upgrade synthetic gas into renewable natural gas (RNG).
    • Construction of an onsite RNG pipeline injection point.

Notable Quotes

  • "Our team is successfully advancing phase 1 of the Thorold renewable energy facility construction as we continue with commissioning. With the kiln chamber assembled and major process equipment now in place, the project is moving towards first commercial revenues with growth plans behind it. We are focused on building shareholder value and milestones like this are just the beginning steps to a long-term growth plan." — Andrew White, Chief Executive Officer