NMI 0.195 +0.0% TKO 9.87 +4.4% ELD 45.89 +2.2% DG 0.045 +12.5% TNGD 6.33 +3.4% DPM 52.30 +6.1% EPL 0.180 +2.9% NTH 0.160 +3.2% GGM 0.035 +0.0% ITR 3.01 +4.9% CS 13.25 +3.5% EMO 0.325 +1.6% CAN 0.050 −9.1% MOON 7.40 +3.4% FG 0.035 +0.0% SBMI 0.125 +0.0% NMI 0.195 +0.0% TKO 9.87 +4.4% ELD 45.89 +2.2% DG 0.045 +12.5% TNGD 6.33 +3.4% DPM 52.30 +6.1% EPL 0.180 +2.9% NTH 0.160 +3.2% GGM 0.035 +0.0% ITR 3.01 +4.9% CS 13.25 +3.5% EMO 0.325 +1.6% CAN 0.050 −9.1% MOON 7.40 +3.4% FG 0.035 +0.0% SBMI 0.125 +0.0%
Production / Operations

B2Gold's Goose mine reaches commercial production

BTO · Price

Executive Summary

  • B2Gold’s Goose mine in Nunavut, Canada achieved commercial production on Oct. 2 2025 after meeting its internal metric of 30 consecutive days at ≥65% of the mill’s 4,000 tpd design capacity.
  • Average mill throughput during the 30‑day period was 2,652 tpd (66% of design), rising to 3,249 tpd (81.2% of design) in the latter half of September after integration of a supplemental mobile crusher.
  • The company reaffirmed near‑term gold production guidance: 80–110 koz for 2025, ~250 koz for 2026, ~330 koz for 2027, and an average of ~300 koz per year for the first six full years (2026‑2031).

Key Details

  • Commercial Production Metric: 30 consecutive days at ≥65% of design capacity (4,000 tpd).
  • Throughput Performance:
  • Sept 3 – Oct 2 2025: average 2,652 tpd (66% of design).
  • Sept 19 – Oct 2 2025 (post‑mobile crusher integration): average 3,249 tpd (81.2% of design), crushing rate 183 tph (≈4,385 tpd).
  • Mill Capacity Outlook: B2Gold expects the Goose mill to operate near full design capacity (≈4,000 tpd) through Q4 2025.
  • Feed Source: Primarily mined‑out Echo open pit during the 30‑day period; future feed will shift to the Umwelt deposit.
  • Ore Grade & Recovery: Anticipated average grade of 6.5–7.0 g/t Au for Q4 2025; gold recoveries >90% expected moving forward.
  • Production Guidance (based on existing reserves):
  • 2025: 80,000‑110,000 oz Au
  • 2026: ~250,000 oz Au
  • 2027: ~330,000 oz Au
  • 2026‑2031 average: ≈300,000 oz Au per year.
  • CEO Quote (Clive Johnson): Emphasized the milestone’s significance, thanked construction/operations teams and the Kitikmeot Inuit Association, and highlighted Goose as a cornerstone of B2Gold’s production base.
  • Qualified Person: Bill Lytle, SVP & COO, certified under NI 43‑101, approved technical information.