Production / Operations
Aris Mining produces 73,236 oz Au in Q3

ARIS · Price
Executive Summary
- Aris Mining reported Q3 2025 gold production of 73,236 oz, a 25% increase versus Q2 2025.
- Full‑year 2025 production guidance (230,000–275,000 oz) remains on track after commissioning and ramp‑up of the expanded Segovia mill in June 2025.
- Cash balance stood at > $415 million as of Sept. 30 2025, bolstered by $13.2 million proceeds from the sale of the Juby gold project.
Key Details
- Q3 2025 Gold Production: 73,236 oz (↑25% YoQ).
- Q3 2025 Gold Sales: 73,001 oz (↑20% YoQ).
- Segovia Mine Production: ↑27% vs. Q2 2025.
- Marmato Complex Production: ↑8% vs. Q2 2025.
- Cash Position (Sept. 30 2025): > $415 million, including $13.2 million from Juby project sale.
- Full‑Year Guidance: 230,000–275,000 oz of gold for 2025; company tracking above the midpoint.
- Operational Milestones: Expanded Segovia mill commissioned June 2025 and ramping up as scheduled.
Notable Quotes
“With increased production capacity at Segovia, solid operational momentum, a robust financial position and a favourable gold price environment, we are well positioned to deliver a strong finish to 2025 and build further momentum in 2026.” – Neil Woodyer, CEO, Aris Mining Corp.