GOLD 4476.60 −1.4% SILVER 66.75 −1.4% COPPER 6.68 +0.3% OIL 91.48 +0.2% PALLADIUM 1403.90 −2.5% JDN 0.230 +0.0% HVG 0.050 +0.0% AUMN 0.305 −3.2% MNRG 0.095 +0.0% SKP 0.165 +0.0% RME 0.235 +0.0% HAY 0.070 −12.5% TIGR 0.900 +0.0% BAU 0.200 −2.4% BEEP 0.215 +7.5% FOXT 0.175 +0.0% ARA 3.56 +2.0% WCU 0.175 +84.2% SGML 17.10 −2.3% TUF 0.730 −6.4% TNR 0.270 −3.6% GOLD 4476.60 −1.4% SILVER 66.75 −1.4% COPPER 6.68 +0.3% OIL 91.48 +0.2% PALLADIUM 1403.90 −2.5% JDN 0.230 +0.0% HVG 0.050 +0.0% AUMN 0.305 −3.2% MNRG 0.095 +0.0% SKP 0.165 +0.0% RME 0.235 +0.0% HAY 0.070 −12.5% TIGR 0.900 +0.0% BAU 0.200 −2.4% BEEP 0.215 +7.5% FOXT 0.175 +0.0% ARA 3.56 +2.0% WCU 0.175 +84.2% SGML 17.10 −2.3% TUF 0.730 −6.4% TNR 0.270 −3.6%
Technical Study

FRONTIER LITHIUM HIGHLIGHTS RECENT DEVELOPMENTS, RESULTS FOR THE SIX MONTHS ENDED SEPTEMBER 30, 2025 AND AGM RESULTS

FL · Price

Executive Summary

  • Frontier Lithium released its six‑month financial results (ended Sep 30, 2025) showing $14.9 M cash on hand, bolstered by government reimbursements and stock‑option proceeds.
  • The company published a positive Mine‑and‑Mill Feasibility Study forecasting a 31‑year mine life, post‑tax NPV of $932 M and IRR of 17.9%, with a competitive C1 cost of $602/tonne concentrate.
  • An independent EY socioeconomic impact study estimates the project will generate ~$1.5 B GDP, $124 M tax revenue and 2,163 jobs during construction, underscoring its strategic importance to North‑American battery supply chains.

Key Details

  • Cash Position: $14.9 million as of Sep 30 2025; includes $909k government reimbursement and $634k from exercised stock options.
  • Mine & Mill Feasibility Study (FS):
  • Effective date May 28 2025, published Jul 9 2025.
  • Production target: 200,000 t/yr of 6% Li₂O spodumene concentrate (SC6).
  • Post‑tax NPV (8% discount): $932 million; post‑tax IRR: 17.9%.
  • Assumed CG SC6 price: US$1,475/t; USD/CAD = 1.37.
  • Mine life: 31 years supported by reserves at PAK and Spark deposits (grades 1.96% Li₂O and 1.44% Li₂O).
  • C1 cost: $602 per tonne of concentrate sold.
  • Lithium Conversion Facility FS: Initiated, led by Fluor Canada Ltd.; expected completion H1 2027.
  • Exploration Activity: No drilling since Sep 2024; historic Phase I‑XIV results available in NI 43‑101 report (filed Jul 9 2025).
  • Regulatory Milestone: Selected as first participant in Ontario’s “One Project, One Process” framework (Oct 2025) to streamline permitting.
  • EY Socioeconomic Impact Study Findings:
  • Construction phase (3 years): $1.5 B GDP, $124 M tax revenue, 2,163 FTE jobs.
  • Operations phase (30‑year life): $183 M annual GDP contribution, $12 M annual tax revenue, 950 FTE jobs.
  • Corporate Change: Departure of Vice President of Sustainability & External Affairs, David Ewing, effective Dec 12 2025; transition plan in place.
  • Infrastructure Collaboration: Ongoing work with federal/provincial governments and Indigenous communities on all‑season road and power access for future commercial operations.
  • AGM Results: Voting outcomes from the November 27 2025 Annual General Meeting approved all matters/resolutions presented to shareholders.