GOLD 4170.10 +1.5% SILVER 57.16 +2.3% COPPER 6.56 −1.5% OIL 97.97 +3.0% PALLADIUM 1136.00 +3.6% LUN 32.91 +0.6% DLP 0.290 −3.3% VCV 0.065 −13.3% GG 2.89 +1.4% NBLC 0.015 +0.0% SF 0.300 −4.8% ATY 0.215 +2.4% GHL 0.060 −7.7% STND 0.060 −7.7% B 0.550 −3.5% HBM 34.33 −0.5% NTR 98.77 −0.7% SGZ 0.035 +0.0% MKA 0.670 +0.0% LXM 0.175 −18.6% CLCH 1.08 −1.8% GOLD 4170.10 +1.5% SILVER 57.16 +2.3% COPPER 6.56 −1.5% OIL 97.97 +3.0% PALLADIUM 1136.00 +3.6% LUN 32.91 +0.6% DLP 0.290 −3.3% VCV 0.065 −13.3% GG 2.89 +1.4% NBLC 0.015 +0.0% SF 0.300 −4.8% ATY 0.215 +2.4% GHL 0.060 −7.7% STND 0.060 −7.7% B 0.550 −3.5% HBM 34.33 −0.5% NTR 98.77 −0.7% SGZ 0.035 +0.0% MKA 0.670 +0.0% LXM 0.175 −18.6% CLCH 1.08 −1.8%
Production / Operations

Westbridge Renewable Receives final transmission and connection approvals from the Alberta Utilities Commission for Dolcy Solar + Energy Storage Project

WEB · Price

Executive Summary

  • Westbridge Renewable’s subsidiary Dolcy Solar Inc. received final Transmission Line Permit, Licence and Connection Approval from the Alberta Utilities Commission for the Dolcy Solar + Energy Storage Project.
  • The approval clears all discretionary permitting, moving the 300 MWac solar PV and 100 MW/200 MWh battery storage project to “Ready‑to‑Build” status.
  • This is Westbridge’s third Alberta development reaching construction readiness, following the sale of the Georgetown and Sunnynook projects that generated $39 M and $23 M of non‑dilutive cash respectively.

Key Details

  • Regulatory Approval: Decision 30228‑D01‑2025 from the AUC granting Transmission Line Permit & Licence and Connection Approval, including approval of the Needs Identification Document (AESO) and Facility Approvals for Dolcy Solar Inc. and AltaLink Management Ltd.
  • Project Scope:
  • Solar photovoltaic capacity up to 300 MWac.
  • Battery Energy Storage System (BESS) capacity up to 100 MW / 200 MWh.
  • Transmission line: Dolcy 948AL, connecting the facility to Alberta’s grid.
  • Location: Municipal District of Wainwright No. 61, Alberta.
  • Impact: Once operational, the project is expected to supply power to more than 58,000 Alberta homes.
  • Milestone Status: Project now in “Ready‑to‑Build” stage; construction can commence pending financing and other execution steps.
  • Historical Context:
  • Georgetown Project sold to Metlen Energy & Metals (Dec 2023) – generated $39 M non‑dilutive cash.
  • Sunnynook Project sold to Metlen Energy & Metals (Nov 2024) – generated $23 M non‑dilutive cash.
  • Management Comments:
  • Stefano Romanin, Director and CEO: highlighted the approval as the final regulatory milestone confirming Westbridge’s ability to advance projects from concept to construction readiness.
  • Maggie McKenna, Director and COO: noted pride in achieving the milestone amid a challenging regulatory environment.

Notable Quotes

“This approval represents the final regulatory milestone for Dolcy, confirming our ability to originate and advance high‑quality renewable projects from concept to construction readiness.” – Stefano Romanin, Director & CEO

“We are proud to have achieved this important milestone for the Dolcy project, particularly in light of the challenging and ever‑evolving regulatory environment in this Province.” – Maggie McKenna, Director & COO