LithiumBank to acquire 2nd suspended well at Boardwalk
Mr. Rob Shewchuk repots
LITHIUMBANK TO ACQUIRE SECOND WELL FOR RE-ENTRY AND UNLOCK ERA FUNDING AT BOARDWALK LITHIUM PROJECT
Further to LithiumBank Resources Corp.'s news release dated July 17, 2025, the company started a comprehensive work program to unlock $3.9-million in funding from the province of Alberta through the Emissions Reduction Act (ERA). In partnership with the province, LithiumBank is focused on commencing near-term production from the Boardwalk lithium brine project by employing modular direct lithium extraction (DLE) plants. This modular approach will derisk the project by reducing upfront capital while also utilizing existing oil and gas infrastructure.
To this end, LithiumBank has begun the process of acquiring a second suspended, past-producing well located in close proximity to the company's 10-6 well (acquisition announced May 16, 2024) at the 100-per-cent-owned Boardwalk project, located in west-central Alberta, Canada.
The company believes this well, following exploration work, can likely support near-term lithium-brine production as it is in an area that has abundant historic production data and surface/subsurface infrastructure (wells, well pads, pipelines, roads, water, power). In order to complete the well licence transfer to acquire 100-per-cent ownership of the new well, the company requires approval by the Alberta Energy Regulator (AER). The company will announce an update as and when additional information on this transfer of this new well licence becomes available.
As previously announced (July 17, 2025), to qualify for reimbursement of expenses from the ERA, LithiumBank must complete the following milestones:
Complete an additional exploration drill hole through the Leduc formation reservoir at Boardwalk to support an advanced reservoir model, geological model and collect additional brine. This exploration test well is situated so it can be converted into a production well in the future;
Conduct long cycle DLE testing and optimization, focusing on concentration and impurity removal testing, and conversion to lithium carbonate;
Complete a feasibility study at Boardwalk that assesses a low capex (capital expenditure), modular approach to lithium production.
The company anticipates that this well acquisition will initiate the first milestone allowing the company to test the reservoir productivity, collect additional brine for DLE testwork and optimize plant parameters (milestone 2). Results from milestones 1 and 2 are expected to support a National Instrument 43-101 feasibility study to be completed by the end of 2026 for the third milestone. The ERA program will refund the company 50 per cent of eligible expenditures for each of the three milestones as they are completed, up to a total of $3.9-million.
Over the last five years, the company has successfully consolidated all the strategic brine-hosted mineral licences (BHML) at Boardwalk and Park Place covering the Leduc formation. The NI 43-101 resource estimates at Boardwalk and Park Place are both reported as the highest-grade resource estimates in Alberta and together make LithiumBank the largest-known holder of lithium brine resources in North America. The two projects are completely unrestricted by overlapping pore space or carbon sequestration applications/permits allowing for a clearer path toward permitting of the first production of lithium from brines in Alberta.
Equity grant to management
The company has granted stock options to two officers to purchase an aggregate of 300,000 common shares of the company. The stock options will be exercisable at a price of 58 cents per share with an expiry of Nov. 17, 2030.
Qualified person
The information that forms the basis for the scientific and technical information disclosed in this news release was prepared and approved by Kevin Piepgrass, PGeo, who is a qualified person (QP) for the purposes of National Instrument 43-101. Mr. Piepgrass consents and approves of the inclusion of the data in the form and context in which it appears.
About LithiumBank Resources Corp.
LithiumBank Resources is a publicly traded lithium company that is focused on developing its two flagship projects, Boardwalk and Park Place, in Western Canada, which host some of the largest lithium brine resources in North America. The company holds 1,240,140 acres of brown-field brine hosted mineral licences, across three districts in Alberta and Saskatchewan. The company has pilot tested multiple mature direct lithium extraction (DLE) technologies and is working toward establishing commercial lithium production by a modular approach.