URC 4.02 −3.6% BEX 0.085 +6.2% SUM 1.33 +0.8% FMN 0.270 +10.2% PHNM 0.400 +11.1% HDRO 1.11 −6.7% PWM 0.630 +0.0% LIO 0.155 +10.7% NTH 0.160 +1.6% ELEF 0.115 −8.0% DNO 0.430 +0.0% FPC 0.470 +2.2% SVRS 0.405 −4.7% CLV 0.120 +0.0% LXM 0.160 +6.7% TBK 0.305 −3.2% URC 4.02 −3.6% BEX 0.085 +6.2% SUM 1.33 +0.8% FMN 0.270 +10.2% PHNM 0.400 +11.1% HDRO 1.11 −6.7% PWM 0.630 +0.0% LIO 0.155 +10.7% NTH 0.160 +1.6% ELEF 0.115 −8.0% DNO 0.430 +0.0% FPC 0.470 +2.2% SVRS 0.405 −4.7% CLV 0.120 +0.0% LXM 0.160 +6.7% TBK 0.305 −3.2%
Production / Operations

Integra produces 20,653 oz Au at Florida Canyon in Q3

ITR · Price

Executive Summary

  • Integra Resources Corp. reported strong third-quarter 2025 gold production from its Florida Canyon mine, producing 20,653 ounces and selling 20,265 ounces, which aligns with company expectations.
  • The company significantly increased its cash balance to approximately $81.2 million, marking its strongest financial position to date, driven by strong gold prices and operational cash flow.
  • Capital was deployed for mine reinvestment, including capitalized stripping, leach pad expansion (Phase IIIb commissioning expected in Q4 2025), and a fleet revitalization program involving new heavy equipment to reduce rental costs and improve productivity.

Key Details

  • Gold Production: Produced 20,653 ounces of gold and sold 20,265 ounces of gold during Q3 2025.
  • Cash Position: Cash balance increased to US$81.2 million as of September 30, 2025.
  • Production Drivers: Production supported by recovery of gold from Phase IIIa heap leach pad, residual ounces from Phases I and II, increased solution flow rates, and the new carbon-in-column circuit commissioned in late 2024.
  • Guidance: Company expects to meet its full-year 2025 gold production guidance.
  • Operational Challenges & Mitigation: Increased strip ratio due to capitalized waste stripping and ramping up new mining areas. Waste movement increased due to a provisional adjustment in mine sequence to address dust suppression issues caused by a temporary water shortage (resolved by replacing a problematic historic water well).
  • Capital Projects:
    • Construction of Phase IIIb heap leach pad continued; commissioning expected in Q4 2025.
    • Mining fleet revitalization underway: Refurbishment of existing haul trucks and loaders.
    • New equipment orders placed: Eight new 150-ton Caterpillar haul trucks, one new Caterpillar loader, and one new Hitachi mining shovel.
    • Hitachi mining shovel arrived on site for assembly/commissioning in Q4 2025.
    • Delivery of new haul trucks commences in Q4 2025 and continues into Q1 2026.
  • Strategic Impact: New and refurbished equipment expected to reduce reliance on expensive rentals, increase mining productivity, and lower mining cost per ton over the next several years.
  • Financial Reporting: Full Q3 2025 financial results to be filed on SEDAR+ and EDGAR on November 12, 2025.
  • Conference Call: Scheduled for November 13, 2025, at 11:00 a.m. ET / 8:00 a.m. PT.

Notable Quotes

  • "Florida Canyon continues to deliver on expectations, generating meaningful cash flow to fund crucial reinvestment into the mine, while also supporting the company's broader growth strategy." — George Salamis, President, CEO and Director
  • "Excellent production results from Florida Canyon combined with the strong gold price environment have allowed Integra to significantly increase its quarter-over-quarter cash balance to approximately $81-million, marking the company's strongest ever financial position." — George Salamis, President, CEO and Director