Gold 4,000.50 −0.7% Silver 52.00 +1.5% Copper 6.27 +0.5% Oil 86.53 +0.6% Palladium 1,030.00 +0.9% TIG 0.800 +0.0% RVG 0.715 −4.0% FNV 354.26 −2.4% FDY 4.30 −0.5% MAU 16.05 −3.2% VOXR 6.78 −0.6% TLO 7.04 −1.0% NICU 1.95 −5.8% VTEN 0.440 +0.0% AWM 0.025 +0.0% OR 50.79 −1.8% AUXX 5.30 −5.5% TNR 0.420 +40.0% ORCL 0.030 +0.0% ELD 47.71 −5.4% OPW 0.140 −6.7% Gold 4,000.50 −0.7% Silver 52.00 +1.5% Copper 6.27 +0.5% Oil 86.53 +0.6% Palladium 1,030.00 +0.9% TIG 0.800 +0.0% RVG 0.715 −4.0% FNV 354.26 −2.4% FDY 4.30 −0.5% MAU 16.05 −3.2% VOXR 6.78 −0.6% TLO 7.04 −1.0% NICU 1.95 −5.8% VTEN 0.440 +0.0% AWM 0.025 +0.0% OR 50.79 −1.8% AUXX 5.30 −5.5% TNR 0.420 +40.0% ORCL 0.030 +0.0% ELD 47.71 −5.4% OPW 0.140 −6.7%
Other

Canada Nickel hires Ausenco for engineering at Crawford

CNC · Price

Executive Summary

  • Canada Nickel Company Inc. has awarded a contract to Ausenco Engineering Canada ULC to perform detailed engineering for the process plant and supporting infrastructure at the Crawford nickel sulphide project.
  • The appointment of Ausenco marks a significant milestone in the project's development, with the company targeting the commencement of construction by year-end.
  • This move follows recent government endorsements, including a referral to the Major Projects Office and inclusion in Ontario's 'One Project, One Process' framework.

Key Details

  • Contract Scope: Ausenco is responsible for detailed engineering of the process plant and supporting infrastructure, as well as providing overall project support.
  • Construction Timeline: The company is targeting the start of construction on the Crawford project by year-end.
  • Ausenco’s Role & History: Ausenco has partnered with Canada Nickel since the preliminary economic assessment in 2020, the feasibility study in 2023, and the front-end engineering design in 2025.
  • Government Support: The project received significant federal government endorsements, specifically a referral to the Major Projects Office.
  • Provincial Framework: Crawford was recently named to Ontario's 'One Project, One Process' framework.
  • Qualified Person: Stephen J. Balch, PGeo, verified the technical data disclosed in the release.

Notable Quotes

  • Mark Selby, CEO: "After receiving significant endorsements from the federal government... we are very pleased to move to this next stage in Crawford's development with Ausenco... I look forward to continuing our collaboration with Ausenco, whose exceptional track record in the design and delivery of large-scale sulphide processing projects will be invaluable as we progress."
  • Desmond Tranquilla, VP of Capital Projects: "I am excited to continue our long-term relationship with Ausenco as we build an integrated project team to lead the delivery of the Crawford nickel project... I look forward to building out the rest of our team as we advance this nation-building project."
  • Yan Jin, VP, GTA at Ausenco: "We'll leverage our deep understanding of the project and proven experience delivering large-scale greenfield processing plants in Ontario to deliver a capital-efficient design that supports successful execution and long-term, sustainable operations."
Read the original news release →