C3 Metals to work on Jamaica storm recovery

CCCM · Price
Executive Summary
- C3 Metals Inc. reports that its team and equipment in Jamaica are safe following Hurricane Melissa, which made landfall on October 28, 2025.
- The company has suspended exploration activities for an estimated six to eight weeks to allow for infrastructure restoration and to assist the local community with disaster relief efforts.
- Significant damage includes impassable roads, loss of power, and damage to core logging/storage facilities, though drill rigs and core samples remain intact.
Key Details
- Impact of Hurricane Melissa: Landfall occurred on October 28, 2025. Heavy winds and rainfall caused significant debris, uprooted power line poles, and damaged drill pad sites and access trails.
- Asset Status:
- Personnel: Safe, no injuries reported.
- Equipment: Secure and undamaged.
- Core Samples: Secure and undamaged.
- Facilities: Roofs of core logging and storage facilities damaged; structures remain intact.
- Operational Suspension: Exploration activities are suspended for approximately 6–8 weeks to repair infrastructure and assist the community.
- Community Assistance: The company has shifted focus to providing food, water, and power access to vulnerable community members and assisting in clearing landslide debris and repairing homes.
- Super Block Project (50% owned):
- Phase 1 scout drilling program (14 holes, 2,500 meters) is approximately 50% complete.
- Seven holes completed; assays pending for three holes.
- Remaining seven planned holes to be completed once infrastructure is restored.
- Bellas Gate Project (100% owned):
- Freeport-McMoRan Exploration Corp. is funding exploration costs under a previously announced earn-in agreement.
- Two drill holes completed into porphyry prospects; two into a copper redbed prospect.
- Five additional drill holes were planned for the 2025 program; completion pending infrastructure restoration.
- 3-D IP geophysical survey (70 sq km) was partially complete, with data collected over approximately 46 sq km. Remaining grids to be completed when safe.
Notable Quotes
- Dan Symons, President and CEO: "The safety of our work force is our No. 1 priority... The biggest impact to our exploration programs is that several roads used to get to exploration sites are currently impassable. We estimate it will take approximately six to eight weeks to repair and restore necessary infrastructure to continue exploration activities."
- Dan Symons, President and CEO: "Prior to last year, Jamaica had not been hit by a hurricane since 1988. Therefore, it feels a bit unlucky to have hurricanes make landfall over Jamaica two consecutive years... It is times like these where it is important to come together as a community... This will be our team's focus concurrent with infrastructure restoration to our exploration sites."