Production / Operations
Artemis Gold shuts down mill at Blackwater

ARTG · Price
Executive Summary
- Artemis Gold Inc. is experiencing an unplanned mill shutdown at its Blackwater mine due to a ball mill gearbox failure on March 11, 2026.
- A replacement spare gearbox is available, with repairs and mill restart estimated to take 8 to 10 days.
- First quarter 2026 production will be lower than anticipated, but the company is not revising its full-year guidance of 265,000 to 290,000 ounces of gold while evaluating plans to offset the shortfall.
Key Details
- Failure Date: March 11, 2026
- Equipment Failure: Ball mill gearbox failure at the Blackwater mine
- Repair Timeline: Estimated 8 to 10 days to complete repairs and restart mill operations
- Spare Parts: Suitable replacement spare gearbox is available on-site
- Mining Operations: Mining-related activities continue normally during the milling outage
- Maintenance Utilization: Downtime will be used to carry out various maintenance activities originally planned for early Q2 2026
- Q1 2026 Production Impact: Expected to be lower than originally anticipated as a direct result of the mill outage
- Full-Year Production Guidance: Not currently revised; remains at 265,000 to 290,000 ounces of gold
- Recovery Strategy: Company is evaluating operational plans to make up for the Q1 production shortfall caused by the unplanned event