WDO 26.04 −0.9% FVI 11.84 −1.6% OM 1.75 −1.7% ETG 2.99 +0.0% ARTG 31.47 −4.6% LUC 0.163 +1.6% AFM 1.38 +0.0% IMG 20.95 −3.5% CPAU 0.150 +3.5% MMX 0.075 +7.1% IE 12.47 −2.4% SASK 1.09 −1.8% MOG 0.390 +2.6% XIM 0.070 −6.7% S 0.110 −29.0% OMI 0.300 −4.8% WDO 26.04 −0.9% FVI 11.84 −1.6% OM 1.75 −1.7% ETG 2.99 +0.0% ARTG 31.47 −4.6% LUC 0.163 +1.6% AFM 1.38 +0.0% IMG 20.95 −3.5% CPAU 0.150 +3.5% MMX 0.075 +7.1% IE 12.47 −2.4% SASK 1.09 −1.8% MOG 0.390 +2.6% XIM 0.070 −6.7% S 0.110 −29.0% OMI 0.300 −4.8%
Production / Operations

Artemis Gold shuts down mill at Blackwater

ARTG · Price

Executive Summary

  • Artemis Gold Inc. is experiencing an unplanned mill shutdown at its Blackwater mine due to a ball mill gearbox failure on March 11, 2026.
  • A replacement spare gearbox is available, with repairs and mill restart estimated to take 8 to 10 days.
  • First quarter 2026 production will be lower than anticipated, but the company is not revising its full-year guidance of 265,000 to 290,000 ounces of gold while evaluating plans to offset the shortfall.

Key Details

  • Failure Date: March 11, 2026
  • Equipment Failure: Ball mill gearbox failure at the Blackwater mine
  • Repair Timeline: Estimated 8 to 10 days to complete repairs and restart mill operations
  • Spare Parts: Suitable replacement spare gearbox is available on-site
  • Mining Operations: Mining-related activities continue normally during the milling outage
  • Maintenance Utilization: Downtime will be used to carry out various maintenance activities originally planned for early Q2 2026
  • Q1 2026 Production Impact: Expected to be lower than originally anticipated as a direct result of the mill outage
  • Full-Year Production Guidance: Not currently revised; remains at 265,000 to 290,000 ounces of gold
  • Recovery Strategy: Company is evaluating operational plans to make up for the Q1 production shortfall caused by the unplanned event