GLDN 0.055 +0.0% BRON 0.040 +0.0% BTO 5.43 −0.7% ESK 0.365 −2.7% AUMN 0.275 +0.0% GGX 0.040 +0.0% S 0.155 +29.2% NNX 0.035 +0.0% ABX 51.90 −0.6% TTS 2.40 −4.0% FCI 0.400 −9.1% GR 0.075 +0.0% AII 23.38 +12.4% TUNG 1.72 +1.8% LGO 1.01 −2.9% EMM 0.080 +0.0% GLDN 0.055 +0.0% BRON 0.040 +0.0% BTO 5.43 −0.7% ESK 0.365 −2.7% AUMN 0.275 +0.0% GGX 0.040 +0.0% S 0.155 +29.2% NNX 0.035 +0.0% ABX 51.90 −0.6% TTS 2.40 −4.0% FCI 0.400 −9.1% GR 0.075 +0.0% AII 23.38 +12.4% TUNG 1.72 +1.8% LGO 1.01 −2.9% EMM 0.080 +0.0%
Production / Operations

Alaska Hydro submits interest for BC Hydro power call

AKH · Price

Executive Summary

  • Alaska Hydro Corp. has submitted an Expression of Interest (RFEOI) and intends to submit a Request for Power (RFP) to BC Hydro for its proposed 75-megawatt hydroelectric project in northwestern British Columbia.
  • The company faces a critical regulatory hurdle regarding the mandatory 25% First Nations equity participation requirement, stating it currently has no agreement with First Nations and cannot assure such participation will be secured.
  • Key deadlines include a CEAP submission by September 1, 2025, and the final RFP due by January 5, 2026.

Key Details

  • Project Specifications: Proposed 75-megawatt hydroelectric plant, including a dam and storage reservoir, located on More Creek in northwestern British Columbia.
  • BC Hydro Call for Power 2025 (RFP):
    • Submission deadline: On or before January 5, 2026.
    • Requirement: Minimum 25% First Nations equity participation.
    • Status: Company has not yet undertaken the CEAP (Community Engagement and Assessment Process).
    • Risk: Company is not assured that First Nations will participate in equity.
  • BC Hydro RFEOI:
    • Submission deadline: On or before September 8, 2025.
    • Status: Submission already made; may be amended based on BC Hydro comments.
  • CEAP (Community Engagement and Assessment Process):
    • Mandatory submission deadline: On or before September 1, 2025.
    • Amendment deadline: On or before October 2, 2025.
  • Registration:
    • Optional registration deadline: On or before September 12, 2025.
    • Status: Required registration form has been filed.