B 0.150 +0.0% IFOS 2.28 −2.6% IMM 0.060 +0.0% ROCK 3.38 −1.7% NVX 0.250 −7.4% HAR 0.050 +0.0% YGT 0.175 +0.0% GEN 0.070 −nan% CRB 0.040 +14.3% MSA 7.07 +2.2% AEM 204.81 +0.7% OPW 0.105 +5.0% GRL 0.275 −1.8% AIS 0.150 +0.0% CUU 0.580 −1.7% SOMA 0.720 +5.9% B 0.150 +0.0% IFOS 2.28 −2.6% IMM 0.060 +0.0% ROCK 3.38 −1.7% NVX 0.250 −7.4% HAR 0.050 +0.0% YGT 0.175 +0.0% GEN 0.070 −nan% CRB 0.040 +14.3% MSA 7.07 +2.2% AEM 204.81 +0.7% OPW 0.105 +5.0% GRL 0.275 −1.8% AIS 0.150 +0.0% CUU 0.580 −1.7% SOMA 0.720 +5.9%
Technical Study

VIZSLA SILVER FILES FEASIBILITY STUDY TECHNICAL REPORT ON THE PANUCO PROJECT

VZLA · Price

Executive Summary

  • Vizsla Silver filed its NI 43‑101 technical report and feasibility study (FS) for the Panuco silver‑gold project, confirming previously announced economic parameters.
  • The FS projects 17.4 Moz AgEq of annual production over a 9.4‑year mine life, with an after‑tax NPV(5%) of US$1.8 billion, a 111% IRR and a 7‑month payback at $35.50/oz Ag and $3,100/oz Au.
  • The filing makes the detailed technical and economic data publicly available on SEDAR+, EDGAR and the company website.

Key Details

  • Technical Report: “Panuco Project – NI 43‑101 Technical Report and Feasibility Study” filed with an effective date of 2025‑11‑04.
  • Prepared By: Ausenco Engineering Canada ULC, supported by Mining Plus Canada Consulting Ltd. and SGS Canada Inc.
  • Location: Panuco project, Sinaloa, Mexico – 100 % owned by Vizsla Silver.
  • Production Forecast: 17.4 Moz AgEq per year.
  • Mine Life: Initial 9.4 years (subject to future extensions).
  • Economic Highlights:
  • After‑tax NPV (5%) = US$1.8 billion.
  • Internal Rate of Return (IRR) = 111 %.
  • Payback period = 7 months at base metal prices of $35.50/oz Ag and $3,100/oz Au.
  • Access to Report: Available on Vizsla’s SEDAR+ profile, EDGAR, and the company website (www.vizslasilvercorp.com).
  • Forward‑Looking Statements: The release contains extensive forward‑looking statements regarding project development, financing, permitting, construction timing, metal price assumptions, and other risks.