Northwire Canada EditionSaturday, July 11, 2026
Northwire
GLDN 0.055 +0.0% BRON 0.040 +0.0% BTO 5.43 −0.7% ESK 0.365 −2.7% AUMN 0.275 +0.0% GGX 0.040 +0.0% S 0.155 +29.2% NNX 0.035 +0.0% ABX 51.90 −0.6% TTS 2.40 −4.0% FCI 0.400 −9.1% GR 0.075 +0.0% AII 23.38 +12.4% TUNG 1.72 +1.8% LGO 1.01 −2.9% EMM 0.080 +0.0% GLDN 0.055 +0.0% BRON 0.040 +0.0% BTO 5.43 −0.7% ESK 0.365 −2.7% AUMN 0.275 +0.0% GGX 0.040 +0.0% S 0.155 +29.2% NNX 0.035 +0.0% ABX 51.90 −0.6% TTS 2.40 −4.0% FCI 0.400 −9.1% GR 0.075 +0.0% AII 23.38 +12.4% TUNG 1.72 +1.8% LGO 1.01 −2.9% EMM 0.080 +0.0%
Drill Results Routine +

Element79 Gold Completes Phase One Infrastructure Program at Gold Mountain and Initiates Drill Contractor Selection Process

ELEM · Price

Executive Summary

  • Element79 Gold Corp. has successfully completed Phase One field operations at its wholly owned Gold Mountain Project in Nevada, completing critical infrastructure preparation for upcoming exploration.
  • The company has transitioned the project to a drill-ready status and has commenced soliciting and evaluating bids from qualified drilling contractors for its inaugural exploration drill program.
  • The planned drilling campaign will test priority targets identified in a NI 43-101 report, focusing on a large intrusive-related gold system with associated base metals that remains largely untested by modern exploration methods.

Key Details

  • Project Location: Gold Mountain Project, Nevada's Battle Mountain mining district (wholly owned).
  • Phase One Scope Completed: Rehabilitation and improvement of existing access roads, extension of project road infrastructure, and construction of permitted drill pads.
  • Execution & Permitting: Work performed by Pinion Exploration Inc.; completed following the successful renewal of the drilling permit and posting of the reclamation bond.
  • Current Status: Actively soliciting and evaluating bids from qualified drilling contractors for the inaugural Phase One drill program.
  • Technical Targets: Priority targets identified through a NI 43-101 report; project hosts a large intrusive-related gold system with associated copper, molybdenum, silver, lead, and zinc mineralization.
  • Historical Context: Historical drilling and surface work demonstrate widespread mineralization across the project area, which remains largely untested by modern exploration methods.
  • Next Steps & Timeline: Contract award pending completion of the bid review process; further updates regarding drill program timing, scope, and target selection will be provided as planning progresses.
  • Qualified Person: Kim Kirkland, Director of Element79 Gold Corp, Fellow of AusIMM #309585.

Notable Quotes

  • Michael Smith, President and CEO: "The completion of road construction and drill pad development represents a significant milestone for the Gold Mountain Project... The project has now transitioned from permitting and infrastructure preparation into a drill-ready asset. We are actively engaging drilling contractors and look forward to advancing Gold Mountain through its first modern exploration drill campaign."
Read the original news release →

More from Element79 Gold Corp.