GLDN 0.055 +0.0% BRON 0.040 +0.0% BTO 5.43 −0.7% ESK 0.365 −2.7% AUMN 0.275 +0.0% GGX 0.040 +0.0% S 0.155 +29.2% NNX 0.035 +0.0% ABX 51.90 −0.6% TTS 2.40 −4.0% FCI 0.400 −9.1% GR 0.075 +0.0% AII 23.38 +12.4% TUNG 1.72 +1.8% LGO 1.01 −2.9% EMM 0.080 +0.0% GLDN 0.055 +0.0% BRON 0.040 +0.0% BTO 5.43 −0.7% ESK 0.365 −2.7% AUMN 0.275 +0.0% GGX 0.040 +0.0% S 0.155 +29.2% NNX 0.035 +0.0% ABX 51.90 −0.6% TTS 2.40 −4.0% FCI 0.400 −9.1% GR 0.075 +0.0% AII 23.38 +12.4% TUNG 1.72 +1.8% LGO 1.01 −2.9% EMM 0.080 +0.0%
Drill Results Routine +

Great Plains Metals Completes the First Stage of the Farm-in at Yeoval Goodrich

GPS · Price

Executive Summary

  • Great Plains Metals Corp. (GPS) has completed Stage 1 of its earn-in agreement with Godolphin Resources Ltd, successfully securing a 51% interest in the Yeoval Goodrich Project in New South Wales, Australia.
  • The company has fulfilled all Stage 1 commitments (A$1,000,000 expenditure and 500m drilling) and has formally elected to proceed to Stage 2 to earn a 70% interest.
  • Stage 1 exploration included 2,065m of air-core drilling and 1,000m of diamond drilling, significantly advancing geological understanding and strengthening the case for a previously unrecognized porphyry copper-gold system.

Key Details

  • Earn-in Agreement Terms: Signed June 4, 2025, with Godolphin Resources Ltd (ASX: GOD). GPS earned 51% by incurring A$1,000,000 in exploration expenditure and completing a minimum of 500 metres of reverse circulation and/or diamond drilling.
  • Stage 2 Requirements: GPS must incur a further A$1,000,000 in exploration expenditure over the next 12 months and complete a minimum of 500 metres of RC/diamond drilling to increase its interest to 70%.
  • Alternative JV Path: Godolphin has 20 business days from the notice date to elect a 51/49% Joint Venture (favoring GPS), after which Godolphin would be responsible for 49% of future expenditure.
  • Project Funding: GPS completed a private placement of $4.18 million in February 2026 to ensure funding for progression through Stage 2.
  • Stage 1 Exploration Activities: 2,065 metres of shallow air-core drilling completed around the former Goodrich mine and Mt Rose targets, advancing geological understanding.
  • Diamond Drilling Progress: Phase One of the diamond drill program is complete with 4 holes totaling just over 1,000 metres at Goodrich (initial program up to 2,000m commenced May 2026). Assay results are pending.
  • Geological Findings: The historical Goodrich mine and a newly recognized pencil porphyry at Mt Rose appear to be focal points within a widespread hydrothermal system, strengthening the case for a previously unrecognized porphyry copper-gold system at Yeoval Goodrich.
  • Project Location & Tenure: Located ~70 km northwest of Orange, NSW, within the Macquarie Arc/Lachlan Fold Belt. Covers ~290 square kilometres across tenements EL 8538 and EL 9243.
  • Infrastructure & Geology: Area underlain by granites, granodiorites, and volcanics, with over 60 historic mine workings. Project is accessible via sealed/unsealed roads and adjacent to railway infrastructure.
  • Historical Mining: Goodrich Mine operated 1868–1912 (Cu-Au). Mt Rose is located ~2 km south of Goodrich, with limited mining in 1886. Regional exploration has been continuous since the 1960s, primarily at shallow levels.

Notable Quotes

  • Peeyush Varshney, CEO: "Completing the first stage of our earn-in agreement marks a pivotal milestone for GPS at Yeoval Goodrich. We are increasingly confident that a previously unrecognized porphyry copper-gold system may be hosted here. With Phase One of the drill program having been completed we eagerly look forward to the assay results and additional geological modelling with a view to further advance the Project.”