K92 Mining Announces Strong Q4 Production Results - Record Annual Production, Multiple Operational Records, Upper End of Production Guidance Achieved, and Stage 3 Expansion Process Plant Commissioning Completed
Expansion Execution Masterclass: K92 Delivers Stage 3 Under Budget while Meeting High-End Guidance

The most recent news release (January 12, 2026) confirms that K92 Mining has successfully completed the commissioning and performance testing of its 1.2 million tonnes-per-annum (Mtpa) Stage 3 Expansion Process Plant at the Kainantu Gold Mine. Crucially, the plant was delivered under budget. Operationally, the company achieved record annual production of 174,134 oz AuEq, hitting the upper half of its 2025 guidance (160,000 to 185,000 oz AuEq). Q4 2025 production was 47,178 oz AuEq, a strong finish to the year. Management notes that 95% of growth capital for Stage 3 has already been spent or committed as of year-end 2025, leaving the company in a record net-cash position.
This news is materially positive as it marks the successful transition of K92 from a junior producer to a mid-tier operator. - Production Scale: The completion of Stage 3 provides the infrastructure to target ~300,000 oz AuEq per annum, nearly doubling the 2024 production levels. - Financial De-risking: Completing a major expansion under budget in a complex jurisdiction like Papua New Guinea (PNG) is a significant achievement that validates management's execution capabilities. - Cost Efficiency: While All-In Sustaining Costs (AISC) were elevated during the construction phase (guided at $1,460-$1,560 for 2025), the commissioning of the 1.2 Mtpa plant is expected to drive significant economies of scale and lower unit costs starting in H1 2026. - Exploration Synergy: The ramp-up of the Stage 3 plant allows for the potential re-activation of the older Stage 2a plant for future expansions or processing of regional discoveries like Arakompa.
K92 Mining operates the high-grade Kainantu Gold Mine in the Eastern Highlands province of Papua New Guinea. The flagship project consists of the Kora and Judd vein systems, which are known for exceptionally high grades. The company has moved through three expansion stages: - Stage 2/2A: 0.5 - 0.6 Mtpa (Historical). - Stage 3: 1.2 Mtpa (Just completed/Commissioned). - Stage 4: 1.8 Mtpa (Planned for 2027 commissioning). The project is supported by a large land package with high exploration potential, including the Arakompa and Wera prospects.