Boron One Reports Metallurgical Study Results and Identifies Preferred Concentration Process for Third-Party Borate Materials
Boron One validates third-party processing, backing supply alliance talks.

Boron One Holdings Inc. has released the results of a metallurgical study evaluating alternative processing methods for third-party borate materials. Commissioned by the company and completed by Mineral & Mine Backfill Technologies, with laboratory work conducted by the Institute for Technology of Nuclear and Other Mineral Raw Materials, the study identified calcination followed by classification as the preferred concentration method.
The testing demonstrated that feed materials ranging from 19.75% to 42.06% B₂O₃ were successfully upgraded to commercial-grade concentrates containing 44.81% to 55.25% B₂O₃. Recovery rates ranged from 59.0% to 73.64% depending on the feed grade. These results demonstrate the company's ability to process mineralization characteristics that differ materially from its primary Piskanja deposit.
Qualified Person Nenad Rakic, EurGeol, reviewed and approved the technical information. The findings support ongoing discussions with the material supplier regarding a potential strategic relationship or alliance.
Boron One Holdings Inc. released a metallurgical study on November 19, serving as a technical follow-up to a non-binding Heads of Agreement with a multinational manufacturer announced on November 18 and a mineral processing study for the Piskanja deposit released on November 16. The study demonstrates that third-party feed can be upgraded to commercial specifications using conventional methods, a development that reduces feedstock dependency risk and expands the company’s potential supply base beyond the Piskanja resource.
These results align with the company’s stated strategy of offering customized borate products and validate the technical feasibility of sourcing external materials to supplement Piskanja production. While the findings represent an incremental technical milestone that de-risks the commercial pathway outlined in the HoA, they do not alter the underlying project economics, permitting timeline, or capital requirements established in the October 2026 Preliminary Economic Assessment. The announcement reinforces management's execution capability and supports the commercial narrative, though it remains a preparatory step rather than a revenue-generating event.
Boron One Holdings Inc. is a Canadian mining company focused on the development of boron assets in Serbia, centered on its flagship Piskanja Borate Project. The project features a recently updated Preliminary Economic Assessment (October 2026) highlighting strong economics: post-tax NPV of $638.8 million, IRR of 89.0%, initial capex of $79.9 million, and a payback period of less than 12 months.
The company’s Mineral Resource stands at 7.14 million tonnes at 32.4% B₂O₃ (Measured and Indicated). Processing under the PEA outlines a gravity-based, chemical-free flowsheet for colemanite, with hydrometallurgical leaching for boric acid. Water recirculation targets 90%.
The Mining Plan involves underground drift and fill using continuous miners, with backfill using solidifying material and tailings. Additionally, the company holds the Jarandol Basin exploration license (21 km²) positioned between Piskanja and the government-owned Pobrdje boron mine, targeting resource extensions.