TDG Announces Preliminary Economic Assessment for the Shasta Au-Ag Project
TDG’s Shasta project holds a C$1.18 billion NPV anchor, though Class 5 capital expenditure and environmental assessment permits remain pending.

TDG Gold Corp. (TDG) released its first Preliminary Economic Assessment (PEA) for a joint open-pit operation on the 100%-owned Shasta and Mets deposits in the Toodoggone district, British Columbia, with an effective date of November 17, 2026. The study was coordinated by Ausenco, with SRK handling resource and mine design, and Falkirk managing environmental and permitting aspects.
The PEA outlines a 9.9-year operating life at a throughput of approximately 4.0 million tonnes per annum (Mtpa), or 11,000 tonnes per day (tpd). The mine plan schedules 38.21 million tonnes of plant feed with an overall strip ratio of 2.18:1. The operation will utilize an owner-operated truck-and-shovel fleet purchased upfront. The project’s economics include an after-tax net present value at a 5% discount rate (NPV₅) of C$1.18 billion, an after-tax internal rate of return (IRR) of 38.8%, and a payback period of 1.8 years from the start of production. Pre-tax metrics show an NPV₅ of C$1.89 billion and an IRR of 48.3%, resulting in an NPV₅-to-initial-capital ratio of 2.0:1.
Capital costs are estimated at C$604.9 million, including C$92.6 million in contingency. This figure encompasses sustaining capital of C$152.7 million and a closure provision of C$60.0 million. The cost estimate carries an AACE Class 5 accuracy of −30% / +50%. Pre-production spending is scheduled over two years, with C$178.5 million in year −2 and C$426.4 million in year −1.
Production forecasts indicate an average annual payable output of approximately 71,200 ounces of gold (Au), 2.82 million ounces of silver (Ag), and 111,000 ounces of gold equivalent (AuEq). Over the life of mine (LOM), payable production is estimated at 705,300 oz Au, 27.94 moz Ag, and 1.099 moz AuEq. Silver accounts for approximately 36% of LOM gross metal revenue. The all-in sustaining cost (AISC) is projected at US$1,283 per payable AuEq oz. The base case assumes gold at US$3,550/oz, silver at US$50/oz, and an exchange rate of C$1.35/US$1.00.
The assessment incorporates an updated Mineral Resource Estimate (MRE) for Shasta and an inaugural MRE for Mets. The Shasta MRE includes 17.12 million tonnes of Indicated resources at 0.87 g/t Au, 31.73 g/t Ag, and 1.28 g/t AuEq (705 koz AuEq), alongside 26.84 million tonnes of Inferred resources at 0.47 g/t Au, 20.57 g/t Ag, and 0.74 g/t AuEq (636 koz AuEq), at a 0.14 g/t AuEq cut-off. The Mets MRE reports 0.53 million tonnes of Inferred resources at 2.47 g/t Au (42 koz). The company explicitly stated that no new drilling was incorporated into the MRE since the previous estimate dated December 29, 2024. Additionally, the previously reported Baker tailings storage facility MRE has been excluded from the updated MRE, the PEA mine plan, and the economics.
Royalties on the deposits are net smelter return (NSR)-based, with 1.5% on Shasta and 2.0% on Mets. The deposits carry mining leases valid until 2050 and 2053, respectively. The permitting path requires a BC Environmental Assessment Certificate, a federal Impact Assessment Act decision, an amended Mines Act permit (noting that existing M-189 covers only ~175 ha of historical workings), an EMA discharge permit, and a Fisheries Act authorization for the proposed Jock Creek diversion, which is currently scheduled from operating Year 4.
The release restates the November 12, 2026 Freeport agreement, under which TDG receives C$110 million cash for 51% of Aurora West, plus C$80 million in earn-in expenditures and a further C$40 million cash. The agreement confirms that Shasta and Baker are excluded from the deal and remain 100% owned by TDG.
TDG Gold Corp. (TDG) released its first-ever economic study for the Shasta project on November 17, delivering the Preliminary Economic Assessment (PEA) roughly six to seven weeks behind the June 1, 2026 target of Q3 2026. Ausenco served as the lead consultant for the study, which includes the full set of metrics originally promised, covering scale, capital intensity, operating costs, mine life, sensitivities, and optimization opportunities. The substance of the study was not previously in the public domain.
The PEA reports a headline after-tax NPV₅ of C$1.18 billion against a market capitalization of approximately C$207 million, resulting in a modelled NPV₅ per current share of roughly C$4.20. This valuation comes five days after a joint venture with Freeport materially improved the company’s treasury. The sequencing of monetizing Aurora West followed by publishing Shasta economics aligns with signals provided in the December 16, 2025 year-end release and the June 1, 2026 announcement.
Silver economics are a significant component of the project, with average payable silver production of 2.82 moz/year, representing approximately 36% of life-of-mine (LOM) revenue. This aligns with the June 17, 2026 metallurgical release, which indicated a ~38% silver contribution to recovered value.
Internal consistency checks indicate that the Shasta feed of 37.66 Mt at 0.66 g/t Au and 26.99 g/t Ag converts to roughly 1.0 g/t AuEq. This calculation uses stated 91% Au and 90% Ag recoveries, along with 92.4% and 95.0% payabilities, reconciling to the 1.099 moz LOM payable AuEq figure. Metallurgical assumptions in the PEA are conservative compared to testwork; the June 17, 2026 locked-cycle test returned 91.4% Au and 90.0% Ag, while the PEA models 91% Au and 90% Ag.
Price sensitivity analysis shows the project remains viable under stress scenarios. At a −20% reduction on both metals, with gold at US$2,840/oz and silver at US$40/oz, the after-tax NPV₅ is C$703 million, with a 26.7% IRR and a 2.6-year payback period.
The resource grade has decreased rather than improved. The December 16, 2025 release reported a pit-constrained Shasta MRE of 515.8 koz AuEq Indicated at 1.35 g/t and 505.5 koz AuEq Inferred at 1.04 g/t at a 0.40 g/t AuEq cut-off. The current Indicated grade is 1.28 g/t and the Inferred grade is 0.74 g/t at a 0.14 g/t AuEq cut-off. While tonnes and contained ounces have risen, the company attributes the lower grades to higher metal price assumptions lowering the cut-off and expanding the conceptual pit, largely reflecting the inclusion of additional lower-grade material. Nearly two years of drilling at Aurora West, Anyox, and Shasta has not resulted in resource growth for Shasta.
The Mets deposit is presented as a co-equal in headlines but accounts for only 0.53 Mt and 42 koz AuEq. It contributes approximately 1.4% of scheduled plant feed (0.55 Mt of 38.21 Mt) and is scheduled as a high-grade satellite in Years 4–5 after payback. With low recoveries of 77% Au and 60% Ag and no silver payability, it serves as a marginal addition rather than a second pillar.
The project scope has shrunk relative to previous commitments. The June 1, 2026 release stated the PEA would assess the incorporation of Mets mineralization and reprocessing of historical Baker tailings. Mets was included in a limited capacity, while Baker tailings were dropped entirely from the MRE, mine plan, and economics. The June 17, 2026 testwork showed 66% Au and 59% Ag projected recovery from Baker TSF material, explaining the omission, but it represents one of three stated workstreams failing to make the study.
Capital expenditure is a primary uncertainty, classified as AACE Class 5 with a +50% upside range, reaching C$907 million at the top end. The study provides no NPV sensitivity to capex or schedule, only metal price sensitivities. The company cautions that initial capital expenditures do not necessarily represent total external financing required and that the NPV₅-to-initial-capital ratio is not a shareholder return or financing valuation. The C$1.18 billion NPV does not account for a funding gap of approximately C$500+ million beyond Freeport proceeds, plus general and administrative and exploration expenses prior to a construction decision.
Production timing is long-dated. The model discounts to December 31, 2027, with production beginning after two years of pre-production spend. The project requires a BC EA certificate, a federal IAA decision, an amended Mines Act permit, an EMA discharge permit, and Fisheries Act authorization for the Jock Creek diversion. The company states that existing permit M-189 does not by itself permit the integrated operation, suggesting a realistic first-production date is well beyond the 3–6 month window and likely financing cycles.
Prior-period context from the MD&A for the nine months ended April 30, 2026, reported a net loss of $24.1 million versus $2.9 million in the prior-year period. This was driven by a $25.4 million increase in exploration and evaluation expenditures, cash declining from $40.7 million to $9.8 million, and working capital of $10.5 million. The Freeport C$110 million investment, if it closes, represents roughly 18% of initial capital.
TDG Gold Corp. is a TSXV-listed mineral exploration company focused on gold, silver and copper projects in British Columbia. The portfolio is described as roughly 60,000 hectares across the Golden Horseshoe, comprising:
- Shasta gold-silver deposit and Mets prospect (Toodoggone district) — mining leases to 2050 and 2053 respectively, with a historical Mines Act permit (M-189, ~175 ha) and a historical EMA discharge permit (PE-8467) on the Shasta property. This is the flagship asset and the subject of the PEA. Past-producing.
- Baker Complex, including past-producing Baker and the Baker tailings storage facilities. Baker and Shasta are excluded from the Freeport JV and remain 100% TDG.
- Aurora West — the 2025 discovery area, now subject to the Freeport JV: Freeport acquires 51% for C$110 million cash, with an option to reach 75% of the operating JV and 100% of the claims entity via C$80 million of exploration expenditures and a further C$40 million cash.
- Anyox copper project — VMS system acquired via the June 2025 amalgamation with Anyox Copper Ltd.; the 4300 Zone discovery (hole ANY-25-002: 25.08 m at 2.1% CuEq, ~900 m below surface) was reported February 23, 2026 and extended April 1, 2026 (ANY-25-003: 25.7 m at ~2.0% CuEq, 80 m step-out).
Management: Fletcher Morgan, CEO and Director; Paul Geddes, P.Geo., SVP Business Development & Strategy and the Company's Qualified Person for the PEA (he assumed interim technical oversight after Steven Kramar departed as VP Exploration in June 2026). Note that the VP Exploration role has been vacant or interim-led since June 2026; no permanent replacement has been announced in the materials provided, and the PEA Qualified Person sign-off on the company side rests with a business-development executive rather than a dedicated exploration VP.