Drill Results
Cabral Gold Announces the Results of Infill Drilling at the MG Gold Deposit, Cuiu Cuiu Gold District, Brazil
Gold explorer advancing the Cuiu Cuiu project

Executive Summary
- On April 7 2026 Cabral Gold released results from an initial batch of 24 shallow reverse‑circulation (RC) infill holes at the MG starter pit in the Cuiu Cuiu gold district, Brazil.
- Notable intercepts include: RC625 – 48 m @ 1.35 g/t Au; RC626 – 17 m @ 2.27 g/t Au from surface; RC633 – 42 m @ 0.64 g/t Au from surface, etc., with several holes showing >0.5 g/t Au over widths ≥30 m and localized high‑grade sub‑intervals (e.g., 1 m @ 31.94 g/t).
- The results confirm significant near‑surface gold‑in‑oxide mineralization, support an upgrade to the current reserve estimate and feed a refined Phase 1 mine plan targeting commercial production in Q4 2026.
- Cabral will complete the remaining infill program (total 68 RC holes, 3,174 m) by month‑end and expand exploration drilling of underlying hard‑rock targets following the C$20 M bought‑deal financing announced March 25 2026.
Material Impact
- The news is positive but largely expected: it follows a previously announced infill drilling program tied to the recent $20 M bought‑deal financing and aligns with the company’s stated goal of upgrading the MG starter pit reserve ahead of Phase 1 production.
- No new, unexpected catalyst (e.g., a major discovery, surprise financing, or permitting breakthrough) is presented; rather it validates ongoing work already disclosed in prior releases (high‑grade Jerimum Cima intercepts, LP permit, construction progress).
- Consequently the impact is routine‑positive – incremental confirmation that keeps the project on track but does not materially alter valuation beyond what was already priced in.
CBR · Price
Company Overview
- Cabral Gold Inc. is a TSX‑V listed explorer focused on advancing its Cuiu Cuiu gold district in Pará, Brazil.
- The flagship asset is the Phase 1 heap‑leach starter operation targeting near‑surface gold‑in‑oxide material from the MG, Central and Machichie deposits.
- Updated PFS (July 2025) indicates:
- Indicated resources – fresh basement: 12.29 Mt @ 1.14 g/t Au (~450,200 oz); oxide: 13.56 Mt @ 0.50 g/t Au (~216,182 oz).
- Inferred resources – fresh basement: 13.63 Mt @ 1.04 g/t Au (~455,100 oz); oxide: 6.4 Mt @ 0.34 g/t Au (~70,569 oz).
- Planned capacity: 1 Mtpa heap‑leach plant; mine life ~6.2 years; AISC US$1,210/oz; IRR 78%; NPV₅ US$74 M (base case $2,500/oz gold).
- Commercial production targeted for Q4 2026 following plant commissioning in Q3 2026.
More from Cabral Gold Inc.
Jul 21, 2026 · 06:30