Gold 4,033.10 +0.0% Silver 52.06 −0.3% Copper 6.58 −0.2% Oil 102.80 +0.8% Palladium 1,002.00 +0.3% ONAU 0.530 −1.9% WMS 0.075 +0.0% CAD 2.34 −2.5% NGEX 21.53 −1.3% CG 28.52 −3.7% PPX 0.220 −8.3% CS 11.77 −2.1% EMO 0.295 +0.0% IPT 0.225 +0.0% TECK 89.22 +1.3% SLG 5.95 +0.8% FT 0.095 +2.7% SGQ 0.330 +6.5% AUAU 0.440 +6.0% FVL 0.830 −2.4% AYA 34.15 −3.3% Gold 4,033.10 +0.0% Silver 52.06 −0.3% Copper 6.58 −0.2% Oil 102.80 +0.8% Palladium 1,002.00 +0.3% ONAU 0.530 −1.9% WMS 0.075 +0.0% CAD 2.34 −2.5% NGEX 21.53 −1.3% CG 28.52 −3.7% PPX 0.220 −8.3% CS 11.77 −2.1% EMO 0.295 +0.0% IPT 0.225 +0.0% TECK 89.22 +1.3% SLG 5.95 +0.8% FT 0.095 +2.7% SGQ 0.330 +6.5% AUAU 0.440 +6.0% FVL 0.830 −2.4% AYA 34.15 −3.3%
Production / Operations Routine +

Silver Mountain Reports 75% Completion of Processing Plant Rehabilitation Activities at Reliquias

Reliquias Plant Rehabilitation Nears Completion as Reserve Definition Risks Loom

Executive Summary
  • Operational Progress: Silver Mountain Resources reports 75% completion of rehabilitation activities at its 100%-owned Reliquias processing plant in Peru.
  • Testing Milestones: Successful empty-load testing completed on key crushing, grinding, and flotation circuits with no operational issues identified.
  • Production Timeline: The company targets a production restart at the Reliquias plant in Q3 2026.
  • Next Steps: Upcoming phases include mechanical completion, electrical integration, instrumentation installation, and dry commissioning activities.
  • Financial Position: Management states the Company remains well funded to support the planned restart of operations.
Material Impact
  • Confirmation of Guidance: The news confirms the Q3 2026 production restart timeline previously communicated in April 2026 (NewsId 1845268 vs NewsId 94239). It does not introduce new unexpected catalysts or delays.
  • Execution Validation: Successful empty-load testing is a positive operational milestone that de-risks the mechanical restart, but it does not address resource certainty.
  • Contextual Risk (Reserve Correction): The most recent news must be weighed against the May 1, 2026 Annual Filing correction (NewsId 1379117), which clarified that no mineral reserves as defined under NI 43-101 have been established at Reliquias. This creates a fundamental disconnect between operational readiness and resource definition risk.
  • Market Expectation: The market has already priced in the restart timeline, evidenced by the price surge to $5.91 in February 2026 followed by consolidation. This update is incremental confirmation rather than a game-changer.
AGMR · Price
Company Overview
  • Company: Silver Mountain Resources Inc. (TSX: AGMR).
  • Flagship Project: Reliquias Mine, Peru. A past-producing underground silver mine.
  • Development Status: Transitioning from development to production. Processing plant rehabilitation is 75% complete. Underground development exceeded 3,000 metres (April 2026 update).
  • Infrastructure: Tailings storage facility completed and operational. Camp infrastructure rehabilitated. Power lines and water treatment facilities operational.
  • Ore Stockpile: Approximately 12,000 tonnes of ore stockpiled as of April 2026 to support initial plant feed.
Read the original news release →