NIO 0.135 −3.6% III 7.22 −2.8% NCAU 0.295 −3.3% NEV 0.040 +0.0% ITR 3.00 −1.6% ALDE 2.79 −0.7% TECK 84.18 +4.4% FVI 11.83 −2.2% SUM 1.31 −1.5% RSMX 0.115 +4.5% STW 0.105 +5.0% PAT 0.250 +0.0% CCM 0.520 +0.0% SGN 0.255 +0.0% CNC 1.49 +1.4% PHNM 0.345 +6.2% NIO 0.135 −3.6% III 7.22 −2.8% NCAU 0.295 −3.3% NEV 0.040 +0.0% ITR 3.00 −1.6% ALDE 2.79 −0.7% TECK 84.18 +4.4% FVI 11.83 −2.2% SUM 1.31 −1.5% RSMX 0.115 +4.5% STW 0.105 +5.0% PAT 0.250 +0.0% CCM 0.520 +0.0% SGN 0.255 +0.0% CNC 1.49 +1.4% PHNM 0.345 +6.2%
Production / Operations

Silver Mountain Resources Provides Operational Update on Reliquias Restart and District Drilling Programs

Silver Mountain Hits Development Milestones as Reliquias Restart De-Risks with US$32M Treasury

Executive Summary

The news release on January 14, 2026, provides a comprehensive operational update on the Reliquias Mine restart in Peru. Key highlights include the completion of 1,500 metres of underground development and the accumulation of a 2,500-tonne mineralized stockpile. The company confirmed that processing plant refurbishment and tailings storage facility rehabilitation are on schedule for a Q3 2026 commercial production restart. Additionally, Silver Mountain announced a significant 17,000-metre drilling campaign, split between infill drilling at Reliquias (7,000m) and exploration at the nearby Caudalosa Mine (10,000m). Financially, the company reported a robust treasury exceeding US$32 million.

Material Impact

This update is materially positive as it demonstrates successful execution against the timeline established in mid-2025. - Execution Milestone: The 1,500m of development and growing stockpile are tangible proof of operational ramp-up. - Financial De-risking: The US$32 million treasury, following two major financings in 2025 totaling approximately C$55 million, provides enough runway to reach the Q3 2026 production target without immediate dilution. - Growth Catalyst: The 10,000m program at Caudalosa indicates management is shifting from pure rehabilitation to expanding the resource base, which provides exploration upside beyond the initial 8-year mine life. - Consistency: The target for commercial production remains Q3 2026, showing no slippage in the timeline despite the complexities of mine restarts in Peru.

AGMR · Price
Company Overview

Silver Mountain Resources is focused on restarting the Reliquias silver-polymetallic mine in Huancavelica, Peru. The project is a past-producer with existing underground infrastructure and a processing plant. The company’s strategy is to modernize the facility to produce approximately 2.5 million silver-equivalent ounces annually over an initial 8-year mine life. The project is 100% owned and located in a prolific mining district.