Northwire Canada EditionSunday, July 26, 2026
Northwire
B 0.150 +0.0% IFOS 2.28 −2.6% IMM 0.060 +0.0% ROCK 3.38 −1.7% NVX 0.250 −7.4% HAR 0.050 +0.0% YGT 0.175 +0.0% GEN 0.070 −nan% CRB 0.040 +14.3% MSA 7.07 +2.2% AEM 204.81 +0.7% OPW 0.105 +5.0% GRL 0.275 −1.8% AIS 0.150 +0.0% CUU 0.580 −1.7% SOMA 0.720 +5.9% B 0.150 +0.0% IFOS 2.28 −2.6% IMM 0.060 +0.0% ROCK 3.38 −1.7% NVX 0.250 −7.4% HAR 0.050 +0.0% YGT 0.175 +0.0% GEN 0.070 −nan% CRB 0.040 +14.3% MSA 7.07 +2.2% AEM 204.81 +0.7% OPW 0.105 +5.0% GRL 0.275 −1.8% AIS 0.150 +0.0% CUU 0.580 −1.7% SOMA 0.720 +5.9%
Production / Operations

DPM Metals Achieves Gold Production Guidance for the Eleventh Consecutive Year; Announces Timing of Fourth Quarter and Full-Year 2025 Financial Results

DPM · Price

Executive Summary

  • DPM Metals released preliminary Q4 2025 and full‑year 2025 production results for its Chelopech, Ada Tepe and Vareš operations.
  • Consolidated 2025 production reached 244.9 koz of gold and 30.0 MLbs of copper, meeting the company’s eleven‑year streak of achieving gold guidance.
  • The company reaffirmed its target to ramp Vareš to an 850,000‑tonne per year operating rate by end‑2026 and will provide a three‑year outlook with detailed 2026 guidance on Feb 10, 2026.

Key Details

  • Q4 2025 Consolidated Production (excluding Vareš):
  • Ore processed: 786 Kt
  • Gold contained in concentrate: 70.2 koz
  • Copper contained in concentrate: 9.9 MLbs
  • Payable gold sold: 63.4 koz
  • Payable copper sold: 7.6 MLbs

  • Full‑Year 2025 Consolidated Production (excluding Vareš):

  • Ore processed: 2,978 Kt
  • Gold contained in concentrate: 244.9 koz
  • Copper contained in concentrate: 30.0 MLbs
  • Payable gold sold: 219.0 koz
  • Payable copper sold: 24.8 MLbs

  • Chelopech Mine – Q4 2025: 45,700 oz Au and 9.9 MLbs Cu produced.

  • Ada Tepe Mine – Q4 2025: 24,500 oz Au produced (no copper).

  • Vareš Operation – Q4 2025 & Sep‑Dec 2025:

  • Q4 2025 ore processed: 43.8 Kt → 1.8 koz Au, 242.7 koz Ag, 477 klb Cu, 3,677 klb Pb, 4,961 klb Zn.
  • Sep 3‑Dec 31 2025 ore processed: 78.9 Kt → 5.9 koz Au, 533.4 koz Ag, 1,071 klb Cu, 8,599 klb Pb, 11,857 klb Zn.

  • Guidance Alignment (2025):

  • Chelopech: Production within guidance range of 2,090‑2,200 Kt ore, 160‑185 koz Au, 28‑33 MLbs Cu.
  • Ada Tepe: Production within guidance range of 610‑700 Kt ore, 65‑80 koz Au.

  • Future Outlook:

  • Vareš expected to ramp to commercial production by end‑2026 with higher ore throughput and improved gold/silver grades versus the April 1 2025 Technical Report.
  • Detailed three‑year outlook and 2026 guidance to be released after market close on Feb 10, 2026; conference call scheduled for Feb 11, 2026 at 9 AM EST (registration link provided).

  • Technical Review: Information reviewed and approved by Ross Overall, Director, Corporate Technical Services – a Qualified Person under NI 43‑101.

Notable Quotes

“We ended 2025 on a very strong note, with Ada Tepe and Chelopech delivering the highest quarterly production of the year… 2025 marks the eleventh consecutive year we have achieved our gold production guidance.” – David Rae, President & CEO, DPM Metals.


Materiality Assessment: Material – Positive (preliminary production results that meet/exceed guidance and provide forward‑looking operational outlook).

Read the original news release →

More from DPM Metals Inc.