Production / Operations
LibertyStream Enters Final Installation and Commissioning Prep in Texas, Positioning for Q4 2025 Bulk Lithium Carbonate Production

LIB · Price
Executive Summary
- LibertyStream announced that site preparation has begun for its Lithium Carbonate Refining Unit, moving the project into the final de‑risking phase and targeting initial lithium carbonate production in Q4 2025.
- The company outlined a detailed timeline for concrete work, equipment installation, initial runs, and start of production, positioning full‑scale operations for 2026.
- Concurrently, LibertyStream granted 2,000,000 stock options to consultants under its omnibus equity incentive plan, exercisable at $0.245 per share with quarterly vesting over twelve months.
Key Details
- Site Preparation Commencement: Concrete pads and secondary containment are being installed onsite adjacent to the DLE field unit.
- Refining Unit Phases:
- Softening & Polishing – prepares lithium‑chloride feed for crystallization.
- Technical‑Grade Lithium Carbonate – produces consistent Li₂CO₃ for industrial use.
- Battery‑Grade Finishing – upgrades product to high‑purity battery specifications.
- Project Timeline:
- Early Oct 2025 – Concrete and secondary containment completed.
- Late Oct 2025 – Onsite equipment installation and system tie‑ins.
- Early Nov 2025 – Initial runs and QA validation.
- Q4 2025 (2nd half) – Commencement of lithium carbonate production.
- Future Outlook: Full‑scale commercial operations are targeted for 2026, contingent on successful commissioning and validation of the Refining Unit.
- Option Grant Details: 2,000,000 options granted to certain consultants; exercise price $0.245 per share; vest quarterly over 12 months starting Oct 7 2025; expire Oct 7 2030.
Notable Quotes
“We are very pleased that site preparation is underway for our lithium carbonate Refining Unit… As we enter the fourth quarter, the commissioning of our refining unit and subsequent conversion of stockpiled lithium chloride eluate into commercial‑grade lithium carbonate marks the final critical step toward launching full‑scale operations in 2026.” – Alex Wylie, President & CEO
All forward‑looking statements are subject to risks and uncertainties as described in the release.