Production / Operations
Libertystream begins site prep for Li2CO3 refining unit

LIB · Price
Executive Summary
- Libertystream Infrastructure Partners Inc. has begun site‑preparation for its lithium carbonate refining unit in Texas, moving into the final installation and commissioning phase slated for Q4 2025.
- The company outlines a detailed timeline for concrete work, equipment tie‑ins, initial runs, and the start of commercial lithium carbonate production in the second half of 2025.
- Concurrently, Libertystream is granting two million stock options to consultants under its omnibus equity incentive plan at an exercise price of $0.245 per share.
Key Details
- Site preparation commenced: Nine months of preparatory work completed; concrete pads for three refining train phases (softening & polishing, technical‑grade Li₂CO₃, battery‑grade Li₂CO₃) are being installed.
- Project timeline:
- Early Oct 2025 – Concrete and secondary containment installation.
- Late Oct 2025 – On‑site equipment installation and tie‑ins.
- Early Nov 2025 – Initial runs and quality‑assurance validation.
- Q4 2025 (second half) – Commencement of lithium carbonate production.
- Production goal: Full‑scale commercial production of bulk lithium carbonate targeted for 2026 after successful Q4 2025 commissioning.
- Equity incentive grant: Two million stock options granted to consultants; vest quarterly over 12 months starting Oct 7 2025; exercisable at $0.245 per share; five‑year term expiring Oct 7 2030.
Notable Quotes
“We are very pleased that site preparation is under way for our lithium carbonate refining unit… the commissioning of our refining unit and subsequent conversion of stockpiled lithium chloride eluate into commercial‑grade lithium carbonate marks the final critical step toward launching full‑scale operations in 2026.” – Alex Wylie, President & CEO
Materiality Assessment: Non‑Material – Positive (operational progress with no immediate financial impact).