Northwire Canada EditionTuesday, September 22, 2026
Northwire
GOLD 4383.90 −0.9% SILVER 66.53 −0.9% COPPER 6.79 +1.5% OIL 92.37 −3.9% PALLADIUM 1319.50 +0.0% MSC 0.020 +0.0% BRON 0.050 +0.0% ELD 59.44 −1.4% GBML 0.220 +0.0% SUM 1.59 +0.0% ABC 0.015 +0.0% ELE 30.45 +2.2% CDE 27.46 −0.7% LIB 0.990 +1.0% SLVR 1.17 +0.0% NVO 0.075 −6.2% BRO 0.235 +2.2% FMAN 0.415 +0.0% HVG 0.050 +0.0% MSV 0.540 +16.1% SCD 0.185 −2.6% GOLD 4383.90 −0.9% SILVER 66.53 −0.9% COPPER 6.79 +1.5% OIL 92.37 −3.9% PALLADIUM 1319.50 +0.0% MSC 0.020 +0.0% BRON 0.050 +0.0% ELD 59.44 −1.4% GBML 0.220 +0.0% SUM 1.59 +0.0% ABC 0.015 +0.0% ELE 30.45 +2.2% CDE 27.46 −0.7% LIB 0.990 +1.0% SLVR 1.17 +0.0% NVO 0.075 −6.2% BRO 0.235 +2.2% FMAN 0.415 +0.0% HVG 0.050 +0.0% MSV 0.540 +16.1% SCD 0.185 −2.6%
Resource Estimate

Clean Air Metals PEA Delivers C$219.4 M pre-tax NPV, 39% IRR for the Thunder Bay North Project

AIR · Price

Executive Summary

  • Clean Air Metals released a PEA for the Thunder Bay North project showing a pre‑tax NPV₈ of C$219.4 M, after‑tax NPV₈ of C$157.5 M and an IRR of 39% (pre‑tax) / 32% (after‑tax).
  • Updated resource totals 14.90 Mt indicated and 2.49 Mt inferred, grading 2.66 g/t 2PGE, 0.40 % Cu and 0.24 % Ni; no reserves are declared.
  • The study outlines an 11‑year mine life (plus 2 years pre‑production), 2,500 t/d production rate, initial CAPEX C$89.5 M, sustaining CAPEX C$162.7 M, and a payback period of ~2.5 years with operating margin of ~45%.

Key Details

  • Economic Highlights
  • Pre‑tax NPV₈: C$219.4 M; After‑tax NPV₈: C$157.5 M
  • Pre‑tax IRR: 39%; After‑tax IRR: 32%
  • Spot‑price scenario NPV₈ (pre‑tax): $316 M; IRR: 52%
  • Capital payback: 2.5 years from production start

  • Project Scope

  • Mine life: 11 years + 2 years pre‑production
  • Production: 2,500 t/d (0.91 Mtpa) from underground ramp‑access operation
  • Total mill feed: 8,705 kt; LOM feed grade: 4.92 g/t Pt‑eq

  • Capital & Cost Structure

  • Initial CAPEX: C$89.5 M (including 25% contingency)
  • Sustaining CAPEX: C$162.7 M (total capital C$257.2 M)
  • Operating cost: $100.40/tonne feed; Mine operating cost $66.80/tonne, Toll‑milling $33.60/tonne

  • Resource Update

  • Indicated: 14.90 Mt @ 2.66 g/t 2PGE, 0.40 % Cu, 0.24 % Ni
  • Inferred: 2.49 Mt @ 1.62 g/t 2PGE, 0.31 % Cu, 0.19 % Ni

  • Metallurgical & Payability (toll‑milling scenario)

  • Consolidated payability: Pt 68%, Pd 77%, Au 40%, Ag 21%, Cu 84%, Ni 32%

  • Sensitivity Analyses – economics most sensitive to operating cost variations and metal price changes (tables detail NPV impacts for ±10‑20 % cost shifts and metal price scenarios).

  • Strategic Intent & Next Steps

  • Board approved fast‑track to final production decision.
  • Planned activities: advance NI 43‑101 studies, permitting, Indigenous consultation, explore processing options (including potential acquisition of nearby LDI toll‑milling assets), raise capital, and develop construction financing plan.

  • Quotes

  • CEO Mike Garbutt: “The PEA is a critical step…low‑risk, quick‑payback project…strong government support…best time to move forward.”
  • Chair Jim Gallagher: “Board pleased with results…high‑grade material close to surface…potential for longer mine life.”

  • Technical Review – Independent Qualified Persons (SLR, Technica Mining, XPS, Story Environmental) prepared the PEA; full report to be filed on SEDAR+ within 45 days.

Notable Quotes

“The PEA is a critical step in advancing the Thunder Bay North Project and more importantly, it adds to the list of significant critical mineral opportunities in this province…” – Mike Garbutt, CEO
“The Board is quite pleased with the results of the study…low‑risk, quick‑payback project.” – Jim Gallagher, Chair

Read the original news release →

More from Clean Air Metals Inc.