- Troy Minerals reports significant milestones toward securing an Operating Mining Permit for the Tsagaan Zalaa Silica Project in Mongolia, with a mining license expected in early November 2025.
- Key technical and environmental studies are on schedule, with final permit submission targeted for December 2025.
- The company is actively engaging HP‑grade quartz (HPQ) off‑take partners and conducting metallurgical sampling to position the project for production in 2026.
Key Details
- Registration of high‑purity quartz silica resources approved by a 15‑member council of Mongolia’s Mineral Resources and Petroleum Authority – a prerequisite for the mining license.
- Physical Mining License certificate anticipated early November 2025; full Operating Permit expected late 2025 or early 2026.
- Completed items: detailed technical & economic studies for resource utilization and export.
- In‑progress items (with target completion dates):
- Environmental Impact Assessment – Nov 2025
- Local Government Agreement with CSR plan – Nov 2025
- Blasting Permit application & land Quality Assurance plans – Dec 2025
- Environmental Management Plan & Emergency Response Plan – Nov 2025
- Project location: Saikhandulaan Soum, Dornogovi Province, ~95 km west of Sainshand (major highway/rail hub) and ~200 km from the Chinese border, facilitating export logistics.
- Business development activities: discussions with HPQ specialists and potential off‑take partners across Central & East Asia; metallurgical sampling by independent Chinese labs; early evaluations with solar and semiconductor supply chain customers.
- President Yannis Tsitos highlighted recent trips to Mongolia and China, emphasizing growing demand for premium silica in photovoltaic and renewable‑energy sectors and positioning 2026 as a milestone year.
Notable Quotes
“We’re extremely pleased with our permitting momentum and business development initiatives, which together position 2026 as a milestone year for both Grand Samsara and Troy Minerals.” – Yannis Tsitos, President, Troy Minerals
Materiality Assessment: Material – Positive (the anticipated operating permit is a critical step toward production and cash flow generation).