OLA 12.90 −3.7% CG 22.70 −2.5% EQX 12.89 −4.0% FM 37.51 −2.3% MNRG 0.080 −11.1% KFR 1.31 +0.8% AUMN 0.275 +0.0% GLB 0.250 +0.0% BHS 0.045 −10.0% EGR 0.025 +0.0% RIO 2.59 −4.1% GEN 0.070 +0.0% MAI 4.39 −2.0% RYR 0.175 +0.0% SCD 0.170 +1.5% SRC 1.75 −2.8% OLA 12.90 −3.7% CG 22.70 −2.5% EQX 12.89 −4.0% FM 37.51 −2.3% MNRG 0.080 −11.1% KFR 1.31 +0.8% AUMN 0.275 +0.0% GLB 0.250 +0.0% BHS 0.045 −10.0% EGR 0.025 +0.0% RIO 2.59 −4.1% GEN 0.070 +0.0% MAI 4.39 −2.0% RYR 0.175 +0.0% SCD 0.170 +1.5% SRC 1.75 −2.8%
Production / Operations

Troy Minerals Updates on the Operational Mining Permit for its Tsagaan Zalaa Silica Project, Mongolia and Initiates Commodity Off-Take Discussions

TROY · Price

Executive Summary

  • Troy Minerals reports significant milestones toward securing an Operating Mining Permit for the Tsagaan Zalaa Silica Project in Mongolia, with a mining license expected in early November 2025.
  • Key technical and environmental studies are on schedule, with final permit submission targeted for December 2025.
  • The company is actively engaging HP‑grade quartz (HPQ) off‑take partners and conducting metallurgical sampling to position the project for production in 2026.

Key Details

  • Registration of high‑purity quartz silica resources approved by a 15‑member council of Mongolia’s Mineral Resources and Petroleum Authority – a prerequisite for the mining license.
  • Physical Mining License certificate anticipated early November 2025; full Operating Permit expected late 2025 or early 2026.
  • Completed items: detailed technical & economic studies for resource utilization and export.
  • In‑progress items (with target completion dates):
  • Environmental Impact Assessment – Nov 2025
  • Local Government Agreement with CSR plan – Nov 2025
  • Blasting Permit application & land Quality Assurance plans – Dec 2025
  • Environmental Management Plan & Emergency Response Plan – Nov 2025
  • Project location: Saikhandulaan Soum, Dornogovi Province, ~95 km west of Sainshand (major highway/rail hub) and ~200 km from the Chinese border, facilitating export logistics.
  • Business development activities: discussions with HPQ specialists and potential off‑take partners across Central & East Asia; metallurgical sampling by independent Chinese labs; early evaluations with solar and semiconductor supply chain customers.
  • President Yannis Tsitos highlighted recent trips to Mongolia and China, emphasizing growing demand for premium silica in photovoltaic and renewable‑energy sectors and positioning 2026 as a milestone year.

Notable Quotes

“We’re extremely pleased with our permitting momentum and business development initiatives, which together position 2026 as a milestone year for both Grand Samsara and Troy Minerals.” – Yannis Tsitos, President, Troy Minerals


Materiality Assessment: Material – Positive (the anticipated operating permit is a critical step toward production and cash flow generation).

Read the original news release →