GOLD 4383.90 −0.9% SILVER 66.53 −0.9% COPPER 6.79 +1.5% OIL 92.37 −3.9% PALLADIUM 1319.50 +0.0% MSC 0.020 +0.0% BRON 0.050 +0.0% ELD 59.44 −1.4% GBML 0.220 +0.0% SUM 1.59 +0.0% ABC 0.015 +0.0% ELE 30.45 +2.2% CDE 27.46 −0.7% LIB 0.990 +1.0% SLVR 1.17 +0.0% NVO 0.075 −6.2% BRO 0.235 +2.2% FMAN 0.415 +0.0% HVG 0.050 +0.0% MSV 0.540 +16.1% SCD 0.185 −2.6% GOLD 4383.90 −0.9% SILVER 66.53 −0.9% COPPER 6.79 +1.5% OIL 92.37 −3.9% PALLADIUM 1319.50 +0.0% MSC 0.020 +0.0% BRON 0.050 +0.0% ELD 59.44 −1.4% GBML 0.220 +0.0% SUM 1.59 +0.0% ABC 0.015 +0.0% ELE 30.45 +2.2% CDE 27.46 −0.7% LIB 0.990 +1.0% SLVR 1.17 +0.0% NVO 0.075 −6.2% BRO 0.235 +2.2% FMAN 0.415 +0.0% HVG 0.050 +0.0% MSV 0.540 +16.1% SCD 0.185 −2.6%
Drill Results

NexMetals Step-Out Holes at Selebi North Validate Down-Plunge Continuity

NEXM · Price

Executive Summary

  • NexMetals Mining reported a significant drill intercept at Selebi North: hole SNUG‑25‑194 intersected 32.60 m of continuous mineralization, including 19.90 m of massive sulphide across five sub‑intervals.
  • The result bridges two major step‑out holes (SNUG‑25‑184 and SNUG‑25‑186), confirming down‑plunge continuity and supporting a potential expansion of the Mineral Resource Estimate (MRE).
  • Concurrently, assay results from Selkirk Mine’s metallurgical program were released, highlighting 219 m @ 1.03 % CuEq in hole SMET‑25‑005 and near‑surface mineralization that could expand the deposit.

Key Details

  • Selebi North – Hole SNUG‑25‑194 (Oct 1 2025)
  • Intercepted 32.60 m of continuous mineralization; 19.90 m massive sulphide across five sub‑intervals.
  • True thickness estimated at 60–65 % of logged interval.
  • Designed to bridge mineralization between step‑out holes SNUG‑25‑184 (183 m down‑plunge) and SNUG‑25‑186 (130 m further step‑out).
  • Demonstrated continuity will be incorporated into a future MRE update, potentially expanding the resource envelope.

  • Planned Follow‑up Work

  • Borehole Electromagnetic (BHEM) surveys to map conductive trends associated with newly intersected massive sulphides and define strike extent.

  • Selkirk Mine – Metallurgical Drill Program (Assay Results released Oct 7 2025)

  • Hole SMET‑25‑005: 219.00 m @ 1.03 % CuEq (0.39 % Cu, 0.33 % Ni, 0.61 ppm Pd, 0.14 ppm Pt).
  • Near‑surface interval: 48.00 m @ 0.57 % CuEq starting at 47 m depth (0.19 % Cu, 0.20 % Ni, 0.34 ppm Pd, 0.08 ppm Pt).
  • Results support validation of legacy data and provide key inputs for a future Selkirk resource model update.

  • Infrastructure Context

  • Selebi North is serviced by a 3.5‑m diameter shaft to the 745 m level and a twin 7° decline ramp to the 900 m level, enabling cost‑efficient drilling campaigns.

  • Strategic Commentary

  • CEO Morgan Lekstrom emphasized that the intersect validates the geological model and will strengthen the updated MRE once assays are received.
  • The company highlights growing demand for copper and nickel in green‑energy applications, noting a 109 % price increase for copper over the past five years (USD $2.36/lb → $4.95/lb).

  • Regulatory & Technical References

  • Mineral Resource Estimate supported by the 2024 Technical Report (NI 43‑101 / S‑K Subpart 1300).
  • Scientific and technical information reviewed and approved by Sharon Taylor, VP Exploration, a qualified person under NI 43‑101.

Notable Quotes

“These results are a critical confirmation point for Selebi North… By bridging two major step‑out holes and intersecting significant massive sulphide intervals, we have validated the down‑plunge continuity and further strengthened our geological model.” – Morgan Lekstrom, CEO, NexMetals Mining.


All forward‑looking statements are subject to risks and uncertainties; actual results may differ.

Read the original news release →