GOLD 4408.90 +0.0% SILVER 65.19 +0.4% COPPER 6.55 +0.0% OIL 100.05 −2.4% PALLADIUM 1323.90 +2.3% PGZ 0.170 +3.0% TMQ 4.55 −1.3% SLI 3.08 −1.0% ROX 0.050 −9.1% USHA 0.045 +0.0% ALGR 0.710 +2.9% MINE 0.120 −4.0% KC 0.330 +4.8% EMO 0.335 +0.0% CCM 0.700 +4.5% MAI 5.97 −0.7% PPM 0.015 +0.0% CRE 0.370 +10.4% MNO 1.87 +0.5% FEO 0.810 +3.9% LBNK 0.680 −4.2% GOLD 4408.90 +0.0% SILVER 65.19 +0.4% COPPER 6.55 +0.0% OIL 100.05 −2.4% PALLADIUM 1323.90 +2.3% PGZ 0.170 +3.0% TMQ 4.55 −1.3% SLI 3.08 −1.0% ROX 0.050 −9.1% USHA 0.045 +0.0% ALGR 0.710 +2.9% MINE 0.120 −4.0% KC 0.330 +4.8% EMO 0.335 +0.0% CCM 0.700 +4.5% MAI 5.97 −0.7% PPM 0.015 +0.0% CRE 0.370 +10.4% MNO 1.87 +0.5% FEO 0.810 +3.9% LBNK 0.680 −4.2%
Technical Study

Lithium Argentina and Ganfeng Announce PPG Scoping Study Results and Stage 1 Environmental Approval

LAR · Price

Executive Summary

  • Lithium Argentina announced the results of a scoping study for the Pozuelos‑Pastos Grandes (PPG) lithium brine project, highlighting a 150,000 tpa LCE production platform with an after‑tax NPV8% of $8.1 billion and IRR of 33% at a $18,000/LCE price.
  • The Salta provincial government issued the Environmental Impact Statement (DIA) for Stage 1, clearing a key permitting hurdle; RIGI application is targeted for H1 2026.
  • Capital cost estimates are $3.3 billion for the full life‑of‑project and $1.1 billion for Stage 1, with operating cash costs of $5,027/t LCE and AISC of $5,351/t.

Key Details

  • Ownership Structure (New JV): Ganfeng – 67%; Lithium Argentina – 33%.
  • Production Capacity: 150,000 tpa LCE in three 50,000 tpa stages; Stage 1: 50,000 tpa.
  • Resource Size: 15.1 Mt LCE measured & indicated (13.2 Mt measured + 1.8 Mt indicated).
  • Economic Highlights (Base Case – $18,000/LCE):
  • After‑tax NPV8%: $8.1 billion
  • After‑tax NPV10%: $5.8 billion
  • IRR: 32.7%
  • Payback period: 7 years
  • Capital Cost Estimates:
  • Full project: $3.3 billion (incl. 16% contingency) – direct costs: $3.125 bn; indirect: $176 m.
  • Stage 1: $1.124 billion (incl. 16% contingency).
  • Operating Cost Estimates:
  • Full‑project cash cost: $5,027/t LCE
  • AISC: $5,351/t LCE
  • Stage 1 cash cost: $5,344/t LCE.
  • Cost Breakdown (Full Project): Reagents $1,444; Energy $1,481; Labour $381; Maintenance $429; Salts harvesting $291; G&A $98; Others $664; Contingency $239.
  • Sensitivity to Lithium Price:
  • At $12,000/LCE → NPV8% $3.6 bn, IRR 21.1% (payback 10 yr).
  • At $20,000/LCE → NPV8% $9.6 bn, IRR 36.1% (payback 6.7 yr).
  • Financing Pathway: Jointly pursuing debt, offtake and minority equity; RIGI regime expected to improve after‑tax cash flow by ~$0.9 bn NPV and raise IRR ~7.6%.
  • Regulatory Milestones: DIA approval for Stage 1 received 7 Nov 2025; RIGI application slated H1 2026.
  • Technical Report: NI 43‑101 compliant report to be filed within 45 days (by late Dec 2025).
  • Webcast/Conference Call: 10 Nov 2025, 8:00 am ET – discussion of Q3 2025 results and scoping study.

Notable Quotes

“We are very pleased to have received environmental approval for Stage 1 from the Salta government… PPG highlights our contribution to Argentina’s growing role in advancing a diversified and competitive global supply chain for lithium chemicals.” – Sam Pigott, President & CEO, Lithium Argentina