WHN 0.375 −2.6% LME 0.140 +3.7% AAUC 30.49 +5.3% GGM 0.040 +14.3% FDY 6.18 +3.2% MOG 0.640 +3.2% NEXM 3.20 +1.3% NCAU 0.330 +3.1% LUC 0.160 +0.0% BTR 0.140 +0.0% SMRV 0.200 −16.7% BIG 0.880 +3.5% URC 3.89 +0.0% ATY 0.250 −2.0% NRM 0.075 +7.1% WMS 0.040 +0.0% WHN 0.375 −2.6% LME 0.140 +3.7% AAUC 30.49 +5.3% GGM 0.040 +14.3% FDY 6.18 +3.2% MOG 0.640 +3.2% NEXM 3.20 +1.3% NCAU 0.330 +3.1% LUC 0.160 +0.0% BTR 0.140 +0.0% SMRV 0.200 −16.7% BIG 0.880 +3.5% URC 3.89 +0.0% ATY 0.250 −2.0% NRM 0.075 +7.1% WMS 0.040 +0.0%
Technical Study

LaFleur Minerals Files PEA Technical Report Supporting Restart of Gold Production at Beacon Gold Mill, Quebec

LFLR · Price

Executive Summary

  • LaFleur Minerals filed an NI 43‑101 technical report detailing its PEA for the Swanson Gold Deposit and the fully‑permitted Beacon Gold Mill.
  • The PEA projects a 65% after‑tax IRR, C$101 million NPV (5% discount) and an AISC of US$1,569/oz, based on a base‑case mill throughput of ~1,250 t/day with expansion potential to 3,000–4,000 t/d.
  • The study confirms no material differences from the company’s March 3, 2026 news release and outlines next steps: engineering studies, bulk sampling, further metallurgical testing, resource‑expansion drilling, and permitting work toward a production decision.

Key Details

  • Technical Report: “Swanson Gold Project – Preliminary Economic Assessment of Delivering Swanson Deposit Mineralized Material to the Beacon Mill” prepared by ERM Consultants Canada Ltd.; dated March 27 2026, effective March 16 2026.
  • Qualified Persons: James Gardner, P.Eng. (Principal Consultant, ERM) and Louis Martin, P.Geo. (Exploration Manager, LaFleur) signed off the technical information.
  • Economic Highlights:
  • After‑tax IRR: 65%
  • NPV (5% discount): C$101 million
  • AISC: US$1,569/oz (base case) – US$2,750/oz gold price scenario also modeled.
  • Production Scenario:
  • Base‑case mill throughput: ≈1,250 t/day (current capacity 750 t/d, with refurbishment).
  • Expansion potential to 3,000–4,000 t/day in longer‑term scenarios.
  • Expected free cash flow generation at the US$2,750/oz gold price base case.
  • Infrastructure:
  • Beacon Gold Mill fully permitted, recently refurbished; replacement cost independently valued at US$71 million.
  • Tailings facility also fully permitted.
  • Utilizes existing road access and potential rail links for material transport from Swanson (≈60 km).
  • Project Scope:
  • District‑scale land package: 19,214 ha in the Abitibi Gold Belt, containing multiple gold zones (Swanson, Bartec, Jolin).
  • Planned initial bulk sample: 100,000 t to validate processing assumptions.
  • Next Steps Post‑PEA:
  • Advance detailed engineering and optimization studies.
  • Conduct additional metallurgical testing and resource expansion drilling at Swanson.
  • Pursue permitting and infrastructure work for bulk sampling and future mining.
  • Move toward a definitive production decision for the Swanson Deposit using the Beacon Mill.
  • CEO Quote: “The filing of our PEA technical report marks a significant milestone… we are well positioned to transition into a gold producer and generate near‑term revenue, with additional scalability and operational flexibility that differentiate us from many junior developers.” – Paul Ténière, CEO & Director

Notable Quotes

  • Paul Ténière, CEO & Director: “The filing of our PEA technical report marks a significant milestone for LaFleur Minerals as we advance toward near‑term gold production… we believe the Company is well positioned to transition into a gold producer and generate near‑term revenue…”

All forward‑looking statements are subject to risks and uncertainties detailed in the release.