Gold 4,130.10 +1.4% Silver 52.70 +1.5% Copper 6.31 +1.1% Oil 87.62 −3.5% Palladium 1,020.00 −9.6% MKA 0.650 +6.6% BEX 0.070 +0.0% RTH 0.035 +0.0% GBU 0.075 +0.0% KCC 0.840 −2.3% NEV 0.025 −16.7% FMAN 0.255 +4.1% MEK 0.035 −12.5% RVG 0.720 +9.1% ABRA 11.35 +2.5% ANOR 0.180 +0.0% LG 0.270 −1.8% SPA 0.225 +2.3% WRLG 0.560 +5.7% FRI 0.065 +0.0% RBZ 0.310 +0.0% Gold 4,130.10 +1.4% Silver 52.70 +1.5% Copper 6.31 +1.1% Oil 87.62 −3.5% Palladium 1,020.00 −9.6% MKA 0.650 +6.6% BEX 0.070 +0.0% RTH 0.035 +0.0% GBU 0.075 +0.0% KCC 0.840 −2.3% NEV 0.025 −16.7% FMAN 0.255 +4.1% MEK 0.035 −12.5% RVG 0.720 +9.1% ABRA 11.35 +2.5% ANOR 0.180 +0.0% LG 0.270 −1.8% SPA 0.225 +2.3% WRLG 0.560 +5.7% FRI 0.065 +0.0% RBZ 0.310 +0.0%
Financings

NMG Files 2025 Financial Reports and Advances Phase-2 Matawinie Mine Toward Construction

NOU · Price

Executive Summary

  • Secured a senior secured project debt commitment of US$335 million from Export Development Canada and Canada Infrastructure Bank to fund Phase‑2 Matawinie Mine construction.
  • Awarded major contracts covering >50% of CAPEX (ABB, Metso, Pomerleau, Manawan‑Fournier, Beauce Atlas) and advanced detailed engineering, indicating construction readiness.
  • Completed a US$20 million public equity offering and holds ≈CA$74 million cash; acquisition of a brownfield site in Bécancour positions the company for first‑stage battery material plant FID in H2‑2026.

Key Details

  • Debt Commitment: US$335 M senior secured project financing letter (EDC & CIB); long tenor, flexible structure, competitive rates, ESG‑aligned terms.
  • Equity Financing: US$20 M public equity raise to fund long‑lead items, detailed engineering, and corporate expenses.
  • CAPEX Coverage: Major contracts awarded for >50% of projected Phase‑2 CAPEX – ABB (120 kV substation), Metso (concentrator & processing equipment), Pomerleau (Construction Manager), Manawan‑Fournier (civil works), Beauce Atlas (structural steel).
  • Commercial Agreements: Offtake and marketing contracts with Panasonic Energy, Traxys, and Government of Canada covering ~75% of future production.
  • Brownfield Acquisition: 143,000 m² site in Bécancour (including 22,000 m² facility) to host first‑stage battery material plant dedicated to Panasonic Energy’s active anode material.
  • FID Timeline: Target FID for Matawinie Mine by H1‑2026; Bécancour Plant FID targeted for H2‑2026.
  • Government Support: Referral of Matawinie Mine to Canada’s Major Projects Office; multiple bilateral MoUs and strategic partnerships announced (Canada‑Japan, Canada‑India, etc.).
  • ESG Performance: No major environmental incidents in 2025; TRIFR = 3.92 at facilities, 0 at worksites; carbon‑neutral status maintained via emissions reductions and VCS‑certified offsets (744 t CO₂e emitted).
  • Cash Position: Approximately CA$74 M as of year‑end 2025.

Notable Quotes

“2025 was a year of discipline and determination… Team Nouveau Monde delivered tangible progress across all pillars of our development roadmap; we are reducing execution risk for our fully integrated graphite platform…” – Eric Desaulniers, Founder, President & CEO


All forward‑looking statements reflect management’s expectations as of the release date.