HBM 31.84 +0.0% CNC 1.58 +0.0% ALGR 0.530 +0.0% MSG 0.205 +0.0% ECU 1.69 +0.0% NAM 0.255 +0.0% FDY 5.56 +0.0% TUNG 1.31 +0.0% ABA 0.095 +0.0% SASK 1.02 +0.0% STRR 0.490 +0.0% VGZ 2.51 +0.0% CCO 123.56 +0.0% FAIR 0.050 +0.0% TI 2.85 +0.0% WGX 4.67 +0.0% HBM 31.84 +0.0% CNC 1.58 +0.0% ALGR 0.530 +0.0% MSG 0.205 +0.0% ECU 1.69 +0.0% NAM 0.255 +0.0% FDY 5.56 +0.0% TUNG 1.31 +0.0% ABA 0.095 +0.0% SASK 1.02 +0.0% STRR 0.490 +0.0% VGZ 2.51 +0.0% CCO 123.56 +0.0% FAIR 0.050 +0.0% TI 2.85 +0.0% WGX 4.67 +0.0%
Production / Operations

Lode Gold completes scoping study at Fremont

LOD · Price

Executive Summary

  • Lode Gold Resources Inc. completed an internal scoping study and is pivoting the Fremont gold project to a 100 % underground bulk‑mining scenario, targeting a pilot plant/test mining phase in early 2028 with full ramp‑up by 2030.
  • The company retained EAS Advisors (New York) and Red Cloud Securities to identify a joint‑venture partner and secure investment for the project’s next development stage.
  • Preliminary Economic Assessment (PEA) figures indicate potential production of ~136,000 oz Au per year at a 4,000 t/d underground rate, with plans to scale up to 6,000 t/d pending further engineering studies.

Key Details

  • Scoping Study Completion: Internal study evaluates a fully underground bulk‑mining model for Fremont, California.
  • Joint‑Venture Partner Search: EAS Advisors and Red Cloud Securities engaged to locate an investment partner; evaluation period of 36 months with final investment decision slated for 2028.
  • Pilot Plant/Test Mining: Planned early‑2028 pilot plant using a portable mill (300–500 t/d) for the first three years, followed by ramp‑up to full production by 2030.
  • Production Outlook:
  • At 4,000 t/d underground processing, PEA forecasts ~136,000 oz Au annually.
  • Potential scale‑up to 6,000 t/d contingent on rock mechanics and engineering results.
  • Resource Basis: 2025 Mineral Resource Estimate (MRE) – 1 M oz measured & indicated, 2 M oz inferred; half of gold resides in stockwork outside veins, unmined to date.
  • Mine Plan Highlights:
  • Utilizes only 20 % of the 3,351‑acre wholly owned patented land, minimizing surface footprint.
  • No open pit; all crushing performed underground; cyanide use eliminated (oxides not processed on site).
  • Access via hanging‑wall metamorphic rocks rather than footwall sedimentary rocks.
  • Engineering Parameters:
  • Average true width of mineralization: 53 m at 1 g/t cut‑off, 17 m at 3 g/t cut‑off.
  • Portable mill capacity: 300–500 t/d (Phase 1).
  • Rehabilitation of part of the existing 23 km underground workings for Phase 1 operations.
  • Historical Context: Fremont was a past‑producing gold mine; only ~8 % of the 2025 MRE resource has been extracted. The project includes >43,000 m drilled, extensive underground infrastructure, and proximity to utilities and transport.
  • Management Comment: Jonathan Hill, Director & Technical Committee Chair, emphasized that the scoping study “underpins a strategy to re‑engineer and restart a past‑producing high‑grade gold mine…providing a significantly important near‑term production base supporting the United States government’s aim of domestic gold production.”

Notable Quotes

  • Jonathan Hill: “This internal scoping study underpins a strategy to re‑engineer and restart a past‑producing high‑grade gold mine at Fremont. This provides a significantly important near‑term production base supporting the United States government's stated aim of supporting domestic gold production.”