S 0.140 +0.0% BNKR 4.40 −2.2% QRO 0.045 +0.0% VCT 0.075 +36.4% PPP 1.15 +0.9% LMG 0.390 +0.0% GRDM 0.140 +0.0% ABRA 13.58 −4.1% WHY 0.295 +1.7% HHH 3.94 −0.2% COS 0.060 +0.0% NOB 0.065 −23.5% MEK 0.055 +0.0% TGOL 0.105 −4.5% FCI 0.400 −7.0% SGQ 0.350 +0.0% S 0.140 +0.0% BNKR 4.40 −2.2% QRO 0.045 +0.0% VCT 0.075 +36.4% PPP 1.15 +0.9% LMG 0.390 +0.0% GRDM 0.140 +0.0% ABRA 13.58 −4.1% WHY 0.295 +1.7% HHH 3.94 −0.2% COS 0.060 +0.0% NOB 0.065 −23.5% MEK 0.055 +0.0% TGOL 0.105 −4.5% FCI 0.400 −7.0% SGQ 0.350 +0.0%
Technical Study

Lode Gold Completed Internal Scoping Study at Fremont, Mariposa; Initiates Process to Seek Joint Venture Partner

LOD · Price

Executive Summary

  • Lode Gold completed an internal scoping study evaluating a full‑underground bulk‑mining scenario for its Fremont gold project in California, targeting a pilot plant/test mining phase in early 2028 and full ramp‑up by 2030.
  • The company has retained EAS Advisors (NY) and Red Cloud Securities to identify a joint‑venture partner and secure investment for the underground pivot.
  • The study proposes scaling the Preliminary Economic Assessment (PEA) from 4,000 tpd to up to 6,000 tpd, eliminating open‑pit mining, cyanide use, and reducing surface footprint; it also outlines a portable mill (300–500 tpd) for Phase 1 pilot operations.

Key Details

  • Scope of Study: 36‑month evaluation with Final Investment Decision (FID) scheduled for 2028.
  • Mining Plan Highlights:
  • Use only 20 % of the 3,351‑acre owned land (surface + mineral rights).
  • 100 % underground mining; no open pit.
  • No cyanide processing – surface oxides (0–60 m) will not be processed on site.
  • Portable mill sized at 300–500 tpd for Phase 1 pilot plant/test mining (first three years).
  • Production Targets:
  • Current PEA (2023) at 4,000 tpd underground predicts 136,000 oz Au per year based on 1 M oz Measured & Indicated and 2 M oz Inferred resources.
  • Potential scale‑up to 6,000 tpd pending rock‑mechanics and engineering studies.
  • Resource Context:
  • Updated 2025 Mineral Resource Estimate (MRE) separates veins and stockwork domains; half of the gold resides in unmined stockwork.
  • Average true width: 53 m at 1 g/t cut‑off; 17 m at 3 g/t cut‑off.
  • Strategic Partnerships: EAS Advisors (New York) and Red Cloud Securities engaged to source a JV partner and investment capital for the underground pivot and pilot plant.
  • Infrastructure & Access: Existing 23 km of underground workings, 14 adits, and proximity to electricity, water, roads, railhead, and port support rapid development.
  • Regulatory & Environmental Benefits: Elimination of cyanide use and reduced surface disturbance align with U.S. government goals for domestic gold production.

Notable Quotes

“This internal scoping study underpins a strategy to re‑engineer and restart a past producing high‑grade gold mine at Fremont. This provides a significantly important near‑term production base supporting the United States government's stated aim of supporting domestic gold production.” – Jonathan Hill, Director and Technical Committee Chair


All forward‑looking statements are subject to risks and uncertainties detailed in the company’s filings.