Northwire Canada EditionFriday, July 17, 2026
Northwire
LUN 33.59 −2.5% NTR 94.27 −1.8% LALI 0.055 −8.3% SCD 0.170 +0.0% HWY 0.370 +0.0% FCI 0.385 +1.3% GGAU 0.180 −5.3% KIRO 0.650 +1.6% LBNK 0.430 +0.0% BARU 0.040 +0.0% VCU 1.09 −4.4% NOBL 0.095 −5.0% SHL 0.355 +0.0% MTS 0.130 +0.0% FYL 0.090 +0.0% NUAG 5.55 +1.8% LUN 33.59 −2.5% NTR 94.27 −1.8% LALI 0.055 −8.3% SCD 0.170 +0.0% HWY 0.370 +0.0% FCI 0.385 +1.3% GGAU 0.180 −5.3% KIRO 0.650 +1.6% LBNK 0.430 +0.0% BARU 0.040 +0.0% VCU 1.09 −4.4% NOBL 0.095 −5.0% SHL 0.355 +0.0% MTS 0.130 +0.0% FYL 0.090 +0.0% NUAG 5.55 +1.8%
Technical Study Material +

Ero Announces Inaugural PEA for Furnas, Outlines Low Capital Intensity Project with a 24-Year Initial Mine Life

ERO · Price

Executive Summary

  • Ero Copper released a PEA for the Furnas Copper‑Gold Project showing an after‑tax NPV (8%) of $2.0 bn and a 27% IRR at base metal prices, rising to $4.7 bn NPV and ~44% IRR at higher copper/gold assumptions.
  • The study projects a 24‑year mine life with average annual production of ≈108 kt Cu‑eq (≈70 kt Cu, 111 koz Au, 532 koz Ag) and LOM capital expenditures of ~$1.3 bn ($16,000 per Cu‑eq tonne).
  • The project is being advanced under a 60% earn‑in agreement with Vale Base Metals; Ero will fund exploration, engineering and permitting work to achieve the earn‑in milestones.

Key Details

  • Project Scope & Life
  • 24‑year initial mine life (open pit + underground) with potential extensions.
  • LOM production: >1.2 Mt Cu, ~2.0 M oz Au, ~9.0 M oz Ag.
  • Average annual copper‑equivalent output: 108 kt (70 kt Cu, 111 koz Au, 532 koz Ag).

  • Economic Highlights

  • After‑tax NPV (8%) @ base prices: $2.0 bn; IRR: 27%.
  • At $6.10/lb Cu & $5,550/oz Au: NPV rises to $4.7 bn; IRR ≈44%.
  • LOM C1 cash cost: $0.30/lb Cu (after by‑product credits).
  • Payback period: ~3.1 years.

  • Capital Expenditures

  • Initial capex: $1,280 M (underground mines $179 M, open pit $132 M, processing plant $410 M, infrastructure $139 M, tailings $48 M, others).
  • Phased expansion capex: $287 M (additional underground, open pit, processing indirect costs).

  • Operating Cost Summary

  • First‑15‑year operating cost: $559 M; LOM total: $837 M.
  • Major cost components: underground mining ($2.66 bn first 15 yr), processing ($1.54 bn), tailings management, transportation.
  • By‑product credits: Gold – $5.09 bn (first 15 yr); Silver – $0.29 bn.

  • Resource Estimate

  • Updated NI 43‑101 resource (100% owned):
    • Indicated: 275.6 Mt @ 0.59% Cu, 0.31 g/t Au, 1.66 g/t Ag.
    • Inferred: 195.9 Mt @ 0.52% Cu, 0.31 g/t Au, 1.34 g/t Ag.
  • Total indicated copper ≈1.61 Mt; gold ≈2.77 M oz; silver ≈14.7 M oz.

  • Exploration & Development

  • Completed ~90 k m historic drilling + 28 k m Phase‑1 (to July 2025).
  • Phase‑2 (≈17 k m) finished Q4 2025; Phase‑3 (~50 k m) planned for 2026.
  • Ongoing work to upgrade inferred resources, extend strike length, and evaluate magnetite by‑product circuit & gravity pre‑concentration.

  • Earn‑In Agreement

  • Ero may earn a 60% interest by completing prescribed drilling, PEA, pre‑feasibility, and definitive feasibility studies within five years of the July 2024 definitive agreement.
  • Vale Base Metals retains 40% and receives up to an 11% free carry on future construction capex.

  • Infrastructure

  • Project located ~50 km from VBM’s Salobo operations; close to paved roads, power substation, cement plant, and rail load‑out facility.
  • Proximity to Parauapebas (≈250 k population) reduces need for new greenfield infrastructure.

  • Qualified Person

  • Mr. Cid Gonçalves Monteiro Filho, SME RM, reviewed and approved technical information per NI 43‑101; full technical report to be filed on SEDAR+ and EDGAR within 45 days.

Notable Quotes

“The results of the PEA on Furnas… reinforce what an exceptional asset it is,” – Makko DeFilippo, President & CEO.


All forward‑looking statements are subject to risks and uncertainties detailed in the release.

Read the original news release →

More from Ero Copper Corp.