Gold 4,000.50 −0.7% Silver 52.00 +1.5% Copper 6.29 +0.9% Oil 86.53 +0.6% Palladium 1,046.10 +2.5% VOXR 6.78 −0.6% TLO 7.04 −1.0% NICU 1.95 −5.8% VTEN 0.440 +0.0% AWM 0.025 +0.0% OR 50.79 −1.8% AUXX 5.30 −5.5% TNR 0.420 +40.0% ORCL 0.030 +0.0% ELD 47.71 −5.4% OPW 0.140 −6.7% CDE 21.43 −1.2% AEM 265.03 −2.0% WDO 27.75 −2.0% BEA 0.090 +0.0% GAU 3.41 −4.2% Gold 4,000.50 −0.7% Silver 52.00 +1.5% Copper 6.29 +0.9% Oil 86.53 +0.6% Palladium 1,046.10 +2.5% VOXR 6.78 −0.6% TLO 7.04 −1.0% NICU 1.95 −5.8% VTEN 0.440 +0.0% AWM 0.025 +0.0% OR 50.79 −1.8% AUXX 5.30 −5.5% TNR 0.420 +40.0% ORCL 0.030 +0.0% ELD 47.71 −5.4% OPW 0.140 −6.7% CDE 21.43 −1.2% AEM 265.03 −2.0% WDO 27.75 −2.0% BEA 0.090 +0.0% GAU 3.41 −4.2%
Production / Operations

EMP METALS COMMENCES RE-ENTRY OPERATIONS ON BRACKISH WATER WELL

EMPS · Price

Executive Summary

  • Service rig arrived on location and has begun re‑entry operations on existing brackish water well 5‑23‑7‑9W2.
  • The 10‑day program will isolate the upper wellbore, perforate the target interval, and swab at maximum rates to obtain water samples and establish a sustained fluid level.
  • Completion of re‑entry will enable planning for integration of the brackish water source into Project Aurora Demonstration Plant, supporting EMP Metals’ low‑salinity water strategy for lithium extraction.

Key Details

  • Well Identification: Existing brackish water well 5‑23‑7‑9W2 located near the Project Aurora Demonstration Plant site.
  • Rig Arrival: Service rig arrived on location as of February 5, 2026 (referencing prior press releases dated Jan 27 and Jan 30, 2026).
  • Work Program Steps:
  • Isolate upper section of existing wellbore.
  • Perforate the targeted brackish water interval.
  • Swab the well at maximum swabbing rates to obtain water samples and establish a sustained fluid level.
  • Timeline: Re‑entry operations and testing are expected to take approximately 10 days to complete.
  • Post‑Re‑Entry Plan: Upon completion, EMP Metals will begin planning integration of the brackish water source into the Project Aurora Demonstration Plant.
  • Project Aurora Context: Joint initiative with Saltworks Technologies Inc.; aims to develop a modular “Hub and Spoke” lithium extraction and refining model and advance full‑scale plant design for a 3,000+ tonne/year commercial refinery.

Notable Quotes

(No direct quotes were provided in the release.)

Read the original news release →

More from EMP Metals Corp.