Northwire Canada EditionSaturday, August 15, 2026
Northwire
ERD 6.16 −1.4% NFG 2.37 +2.2% CLM 0.060 +0.0% GEMG 1.64 +0.0% STGO 1.56 +2.6% WEX 0.580 −3.3% NOBL 0.120 +9.1% LGO 1.00 −3.9% SSE 0.095 +0.0% AAZ 0.040 +0.0% MNRG 0.095 +11.8% RME 0.260 +30.0% NUAG 9.48 +1.3% KRN 0.300 +11.1% EON 0.020 −nan% EMO 0.420 −1.2% ERD 6.16 −1.4% NFG 2.37 +2.2% CLM 0.060 +0.0% GEMG 1.64 +0.0% STGO 1.56 +2.6% WEX 0.580 −3.3% NOBL 0.120 +9.1% LGO 1.00 −3.9% SSE 0.095 +0.0% AAZ 0.040 +0.0% MNRG 0.095 +11.8% RME 0.260 +30.0% NUAG 9.48 +1.3% KRN 0.300 +11.1% EON 0.020 −nan% EMO 0.420 −1.2%
Technical Study

LaFleur Minerals Announces Positive PEA Results for the Swanson Gold Deposit Highlighting Low CAPEX, Robust Economics, and Development Pathway to Gold Production at Its Beacon Gold Mill

LFLR · Price

Executive Summary

  • LaFleur Minerals released a PEA for the Swanson Gold Deposit showing an after‑tax IRR of 65%, NPV (5%) of C$101 million, and a 1.8‑year payback at a US$2,750/oz gold price.
  • Updated 2026 Mineral Resource Estimate adds a 30 % increase to indicated resources – now 2.96 Mt @ 1.69 g/t Au (160 koz) plus inferred resources of 1.08 Mt @ 1.93 g/t Au (66.8 koz).
  • Initial capital requirement is C$31 million for a mill upgrade to 1,250 tpd, with total project life‑cycle costs of C$166 million operating and C$10 million sustaining capital; projected cumulative free cash flow reaches ≈ C$188 million by Year 8.

Key Details

  • Economic Highlights (Base Case – US$2,750/oz Au)
  • After‑tax IRR: 65 %
  • NPV (5% discount): C$101 M
  • Payback period: 1.8 years
  • All‑in Sustaining Cost (AISC): US$1,569/oz

  • Capital & Operating Costs

  • Initial capital cost (incl. 1,250 tpd mill upgrade): C$31 M
  • Additional optional expansion to 3,000 tpd: C$175 M (not in base PEA)
  • Sustaining capital over 7‑year mine life: C$10 M
  • Total operating cost estimate: C$166 M (~C$65/tonne feed)

  • Mineral Resource Estimate (2026)

  • Indicated: 2.96 Mt @ 1.69 g/t Au → 160.3 koz contained gold
    • Open‑pit: 2.735 Mt @ 1.62 g/t Au → 142.5 koz
    • Underground (MSO): 221 kt @ 2.51 g/t Au → 17.8 koz
  • Inferred: 1.08 Mt @ 1.93 g/t Au → 66.8 koz contained gold

    • Open‑pit: 854 kt @ 1.75 g/t Au → 48 koz
    • Underground: 225 kt @ 2.60 g/t Au → 18.8 koz
  • Mill Upgrade & Throughput

  • Existing Beacon Gold Mill (750 tpd) to be upgraded to 1,250 tpd for C$15 M; further expansion to >3,000 tpd would require C$175 M.
  • Expected operating cost reduction from C$42/t to ≈C$28/t with higher throughput.

  • Logistics Advantage

  • Direct CN rail spur links Swanson deposit to mill – rail transport cost C$5/t vs. trucking C$15/t.

  • Free Cash Flow Model

  • Staged ramp‑up: 750 tpd (Year 1) → 1,000 tpd (Year 2) → 1,250 tpd (Year 3).
  • Cumulative free cash flow by Year 8: ≈C$188 M (after ~C$10 M closure costs in Years 7‑8).

  • Sensitivity

  • NPV sensitivity analyzed for gold price range US$1,925–US$5,000/oz, CAPEX/OPEX variations ±30‑40% (Class 4 AACE estimate).

  • Next Steps / Recommendations

  • Continue diamond drilling to increase resource base.
  • Pursue additional feed sources for custom milling and potential regional hub‑and‑spoke model.
  • Advance bulk sample (~100,000 t) and environmental permitting; finalize rail spur relocation with CN.

Notable Quotes

  • Paul Ténière, CEO: “The results of this positive PEA indicate a capital‑efficient development pathway for the Swanson Gold Deposit that leverages our nearby Beacon Mill… we believe Swanson has the potential to evolve into a competitive and short‑term gold development project within the Abitibi Gold Belt.”
Read the original news release →

More from LaFleur Minerals Inc.