Gold 4,037.40 −1.9% Silver 51.35 −2.5% Copper 6.26 −1.3% Oil 86.13 −0.8% Palladium 1,024.75 +0.3% SLG 6.05 −4.0% MSC 0.020 +0.0% MCI 0.140 +0.0% PPM 0.095 +0.0% SMP 0.050 +0.0% FUSE 0.020 −20.0% COPR 0.375 +0.0% WSK 0.170 +0.0% GAL 0.370 −2.6% VCG 1.07 +4.9% LVX 0.250 −26.5% RAMP 0.250 −7.4% QTWO 1.70 +5.6% SUM 1.29 −2.3% SGML 7.53 −9.8% BOGO 0.730 −7.6% Gold 4,037.40 −1.9% Silver 51.35 −2.5% Copper 6.26 −1.3% Oil 86.13 −0.8% Palladium 1,024.75 +0.3% SLG 6.05 −4.0% MSC 0.020 +0.0% MCI 0.140 +0.0% PPM 0.095 +0.0% SMP 0.050 +0.0% FUSE 0.020 −20.0% COPR 0.375 +0.0% WSK 0.170 +0.0% GAL 0.370 −2.6% VCG 1.07 +4.9% LVX 0.250 −26.5% RAMP 0.250 −7.4% QTWO 1.70 +5.6% SUM 1.29 −2.3% SGML 7.53 −9.8% BOGO 0.730 −7.6%
Drill Results

Renforth Advancing Work on Globex's Parbec Gold Royalty Property

GMX · Price

Executive Summary

  • Globex Mining Enterprises provides an operational update on the Parbec gold royalty property, highlighting ongoing stripping activities by Renforth Resources to expose the Cadillac Break deposit.
  • The NI 43‑101 Technical Report (dated May 22 2025) confirms a Measured & Indicated resource of 9.61 Mt @ 0.86 g/t Au (≈265,800 oz) and an Inferred resource of 2.55 Mt @ 1.18 g/t Au (≈97,000 oz).
  • Stripping of a ~325 m × 120 m area is slated to begin in April 2026, generating new structural/geological data to support Renforth’s 2026 drill program and bulk‑sample planning.

Key Details

  • Royalty Position: Globex retains a 3% gross metal royalty on all production from the Parbec property.
  • Resource Estimate (NI 43‑101):
  • Measured & Indicated: 9.61 Mt grading 0.86 g/t Au → ~265,800 oz Au.
  • Inferred: 2.55 Mt grading 1.18 g/t Au → ~97,000 oz Au.
  • Location: Property straddles the Cadillac Break, ≈6 km NW of the Malartic open‑pit mine; includes existing underground access via a ramp to the mineralized zone.
  • Current Work: Renforth is stripping an area approximately 325 m × 120 m to expose the Cadillac Break deposit.
  • Upcoming Activities: Outcrop cleaning and channel sampling are expected to start in April 2026 (or when snow permits).
  • Purpose of Stripping: Generate significant new structural and geological data to underpin Renforth’s 2026 drill program and define a bulk‑sample target area.
  • Infrastructure Advantages: Proximity to the Town of Malartic provides ready access to infrastructure, skilled labour, and supplies.

Notable Quotes

  • “Globex is pleased with the steady advancement of the project which in addition to open‑pit potential already has underground access via a ramp up to the mineralized zone.” – Jack Stoch, Executive Chairman & CEO (Qualified Person under NI 43‑101)
Read the original news release →