Gold 3,883.70 −2.9% Silver 50.05 −3.8% Copper 6.19 −1.6% Oil 88.71 +2.5% Palladium 993.75 −5.0% TDG 0.720 +46.9% PRU 6.07 −3.6% NGEX 21.19 −4.4% TWO 0.370 +0.0% BIG 1.04 +9.5% VCG 1.10 +0.0% SCD 0.145 +0.0% GAL 0.370 −0.7% SAG 0.620 −6.1% VIZ 0.195 +0.0% SAGA 0.375 −6.2% ZEN 0.530 −3.6% GDP 0.230 +0.0% PDN 8.41 +0.0% FL 0.350 −2.8% RIO 2.62 −2.1% Gold 3,883.70 −2.9% Silver 50.05 −3.8% Copper 6.19 −1.6% Oil 88.71 +2.5% Palladium 993.75 −5.0% TDG 0.720 +46.9% PRU 6.07 −3.6% NGEX 21.19 −4.4% TWO 0.370 +0.0% BIG 1.04 +9.5% VCG 1.10 +0.0% SCD 0.145 +0.0% GAL 0.370 −0.7% SAG 0.620 −6.1% VIZ 0.195 +0.0% SAGA 0.375 −6.2% ZEN 0.530 −3.6% GDP 0.230 +0.0% PDN 8.41 +0.0% FL 0.350 −2.8% RIO 2.62 −2.1%
Technical Study

CoTec Holdings Corp. Notes Portfolio Company Magiron Completes Independent Definitive Feasibility Study Confirming Strong Economics and Rapid Restart Pathway

CTH · Price

Executive Summary

  • MagIron LLC completed an independent Definitive Feasibility Study (DFS) and Reserve & Resource Statement for restarting its Plant 4 (MN) and Reynolds Pellet Plant (IN).
  • The base‑case after‑tax NPV is ~US$1.6 billion with a 27.6% IRR; payback ≈3 years 7 months and mine life ≈32 years.
  • CoTec’s ~17% ownership in MagIron translates to an attributable pre‑financing value of roughly US$272 million, underscoring the strategic merit of its investment.

Key Details

  • Feasibility Study: Prepared by Behre Dolbear & Company; effective 14 Jan 2026.
  • Economic Highlights:
  • After‑tax NPV (4.9% discount) ≈ US$1.598 billion.
  • IRR ≈ 27.60%.
  • Payback period ≈ 3 years 7 months.
  • Mine life ≈ 32 years; total LOM production ≈ 84 Mt DR‑grade pellets.
  • Capital & Operating Costs:
  • Up‑front capital ≈ US$435 million (≈US$190 M for mining/rail equipment, to be leased).
  • Life‑of‑mine cash cost ≈ US$92.42 per dry metric tonne FOB Reynolds.
  • Production Profile: Average annual DR‑grade pellet output ≈ 2.6 Mt; target 2.5–2.7 Mt/yr after restart.
  • Project Timeline:
  • Final Investment Decision (FID) targeted early 2026, contingent on financing.
  • Refurbishment/upgrade start mid‑2026; commissioning and ramp‑up early 2027.
  • Asset Context: Existing facilities represent ≈ US$660 M of historical capex with a replacement value > US$1.3 billion, offering capital‑intensity advantage over greenfield builds.
  • CoTec Ownership Impact: 17% stake → attributable pre‑dilution value ≈ US$272 million (based on reported NPV).
  • Qualified Persons: Joseph Kantor, Robert Cameron (Reserves/Resources); John Thompson (Mining Engineering); Mark Jorgenson (Processing); Reinis Sipols (Env & Social) – all independent.

Notable Quotes

“The completion of an independent definitive feasibility study represents an important milestone for MagIron… CoTec’s approximate 17% ownership interest … equates to significant attributable value on a pre‑financing dilution basis… This outcome reinforces the strategic rationale behind our investment approach.” – Julian Treger, CEO, CoTec Holdings Corp.

Read the original news release →