B 0.150 +0.0% IFOS 2.28 −2.6% IMM 0.060 +0.0% ROCK 3.38 −1.7% NVX 0.250 −7.4% HAR 0.050 +0.0% YGT 0.175 +0.0% GEN 0.070 −nan% CRB 0.040 +14.3% MSA 7.07 +2.2% AEM 204.81 +0.7% OPW 0.105 +5.0% GRL 0.275 −1.8% AIS 0.150 +0.0% CUU 0.580 −1.7% SOMA 0.720 +5.9% B 0.150 +0.0% IFOS 2.28 −2.6% IMM 0.060 +0.0% ROCK 3.38 −1.7% NVX 0.250 −7.4% HAR 0.050 +0.0% YGT 0.175 +0.0% GEN 0.070 −nan% CRB 0.040 +14.3% MSA 7.07 +2.2% AEM 204.81 +0.7% OPW 0.105 +5.0% GRL 0.275 −1.8% AIS 0.150 +0.0% CUU 0.580 −1.7% SOMA 0.720 +5.9%
Production / Operations

Following Completion of Expansion Concept Studies HyProMag USA Advances Expansion to Three States Supporting a Path To Triple U.S. Rare Earth Magnet Capacity by 2029

CTH · Price

Executive Summary

  • HyProMag USA completed concept studies for new hubs in South Carolina and Nevada, projecting a three‑fold increase in U.S. NdFeB magnet and alloy production to 4,656 metric tons per year by 2029.
  • The expansion is valued at $2.18 billion post‑tax NPV with a 38.7% real IRR under forecast market prices, supporting the commencement of pre‑feasibility studies and reinforcing HyProMag USA’s intent to pursue a U.S. public listing.
  • CoTec Holdings retains a 60.3% equity interest in HyProMag USA and expects the new plants to create roughly 300 skilled jobs while delivering a low‑carbon footprint (2.35 kg CO₂‑eq/kg NdFeB product).

Key Details

  • Production Capacity Increase: From 1,552 t to 4,656 t of NdFeB per annum across three hubs (Texas, South Carolina, Nevada).
  • Financial Valuation:
  • $1.143 billion post‑tax NPV and 27.6% IRR at current market prices.
  • $2.180 billion post‑tax NPV and 38.7% IRR at forecast market prices.
  • Project Schedule: Commissioning of the three plants planned between 2027 – 2029; Texas Hub not included in this expansion timeline.
  • Modular Scenarios Evaluated:
  • Case 1 – NdFeB alloy powder only (HPMS).
  • Case 2 – Alloy powder + sintered block production.
  • Case 3 – Full integration: alloy powder, sintered block, magnet finishing & packaging.
  • Pre‑feasibility Study Focus: Site selection, product mix, plant configuration, layout, permitting, logistics, and technical marketing for South Carolina and Nevada hubs.
  • Economic Metrics: Post‑tax NPV (7% discount) of $409 M (base case) and $780 M (forecast prices) for the Texas Hub detailed in 2025 Detailed Design.
  • Job Creation: Approximately 300 skilled manufacturing positions anticipated across the new U.S. plants.
  • Carbon Footprint: Independent ISO‑compliant study confirms 2.35 kg CO₂‑eq per kg of sintered NdFeB block for Texas Hub feasibility.
  • Feedstock Security: Co‑location with Intelligent Lifecycle Solutions (ILS) facilities; expansion contingent on securing adequate feedstock and offtake agreements.
  • Equity Ownership: CoTec holds 60.3% of HyProMag USA (50% direct, 10.3% indirect).
  • Strategic Intent: Expansion supports HyProMag USA’s scalable U.S. manufacturing platform and its planned U.S. public listing.

Notable Quotes

“The Expansion Concept Study demonstrates that HyProMag USA's Texas Hub is not a one‑off project, but the foundation of a scalable U.S. manufacturing platform… materially strengthens HyProMag USA's readiness for the next phase of growth and capital markets engagement.” – Julian Treger, CoTec CEO

Read the original news release →