NAM 0.250 +0.0% CRD 0.065 +8.3% OLA 12.90 −3.7% CG 22.70 −2.5% EQX 12.89 −4.0% FM 37.51 −2.3% MNRG 0.080 −11.1% KFR 1.31 +0.8% AUMN 0.275 +0.0% GLB 0.250 +0.0% BHS 0.045 −10.0% EGR 0.025 +0.0% RIO 2.59 −4.1% GEN 0.070 +0.0% MAI 4.39 −2.0% RYR 0.175 +0.0% NAM 0.250 +0.0% CRD 0.065 +8.3% OLA 12.90 −3.7% CG 22.70 −2.5% EQX 12.89 −4.0% FM 37.51 −2.3% MNRG 0.080 −11.1% KFR 1.31 +0.8% AUMN 0.275 +0.0% GLB 0.250 +0.0% BHS 0.045 −10.0% EGR 0.025 +0.0% RIO 2.59 −4.1% GEN 0.070 +0.0% MAI 4.39 −2.0% RYR 0.175 +0.0%
Production / Operations

PPX continues construction of Igor processing plant

PPX · Price

Executive Summary

  • PPX Mining reports the Igor processing plant is 55 % complete, with major equipment (ball mills, jaw crusher, leach tanks) installed and civil works nearing final stages.
  • EPC contractor has begun mechanical assembly in the milling area while JPC Ingenieros continues leach‑tank installation; tailings management earthworks are in their final phase.
  • CEO John Thomas states construction is on schedule and commissioning is expected to begin by year‑end.

Key Details

  • Plant design: 350 tpd carbon‑in‑leach (CIL) and flotation plant for gold and silver dore concentrate.
  • Overall progress: 55 % of total plant; first stage now at 65 % completion.
  • Mechanical equipment installed: two 7 ft × 12 ft ball mills, jaw crusher, mill motors, reduction gearboxes, ring gears, cyclone tower, fines hopper, coarse ore hopper, conveyor‑belt supports.
  • Leach tanks: Four tanks partially assembled; lower sections in place, agitator supports for two tanks installed; final height target 23 ft (7 m).
  • Tailings management area: Earthworks near completion, drainage channels and collection ponds being finished; impermeable membrane and perforated‑tube drain system to be installed; Geotubes will receive tailings slurry with water recycling.
  • Materials: Geomembrane and geotextile sourced from China scheduled to arrive early October.
  • Civil works: Retaining wall for ore loading, circular pedestals for water tanks/thickener, bases of desorption plant under construction.
  • EPC contractor (engineering, procurement & construction) continues parallel civil‑work and mechanical assembly activities.
  • JPC Ingenieros leading leach‑tank fabrication; JM&L preparing tailings area for Geotubes.

Notable Quotes

“Construction is progressing well and commissioning should start at year‑end.” – John Thomas, Chief Executive Officer, PPX Mining Corp.